ITAC Assessment: UD0908
ITAC logo
ITAC Assessment: UD0908
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Fire Protection Clothing
NAICS 315210: Cut and Sew Apparel Contractors
SIC 3842: Orthopedic, Prosthetic, and Surgical Appliances and Supplies
Sales Range $100
M
to 500
M
# of Employees 519
Plant Area 89,000
ft2
Annual Production 78,000
pieces
Production Hrs. Annual 6,864
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $182,994 2,823,547
kWh
Electricity Demand $42,497 6,324
kW-mo/yr
Natural Gas $11,978 1,198
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $81,738 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,079

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $561 - $475
7,323
kWh
$86
-
kW-mo/yr
- - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,576 - $1,334
20,592
kWh
$242
-
kW-mo/yr
- - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,160 $1,000 $982
15,147
kWh
$178
-
kW-mo/yr
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $18,164 $55,583 $24,200
373,402
kWh
$4,387
-
kW-mo/yr
$(-10,423.0) - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $7,198 $1,000 $5,814
89,702
kWh
$1,054
-
kW-mo/yr
$330 - -
06 2.7131: Add area lighting switches $4,592 - $3,785
58,406
kWh
$629
-
kW-mo/yr
$178 - -
07 2.7241: Install outside air damper / economizer on hvac unit $32,358 $66,625 $26,232
404,756
kWh
$6,126
-
kW-mo/yr
- - -
08 2.7224: Reduce space conditioning during non-working hours $1,910 - $1,688
26,039
kWh
- - $222
-
MMBtu
-
09 3.5315: Lease / purchase baler; sell cardboard to recycler $5,140 - - - - - $5,140
10 3.5217: Reuse / recycle/ sell paper products $4,376 $500 - - - - $4,376
11 3.6193: Install equipment (eg compactor) to reduce disposal costs $2,363 - - - - - $2,363
12 3.5316: Contract a wood pallet recycling company $2,340 $3,000 - - - - $2,340
TOTAL RECOMMENDED $81,738 $127,708 $64,510
995,367
kWh
$12,702
-
kW-mo/yr
$(-9,915.0) $222
-
MMBtu
$14,219
TOTAL IMPLEMENTED $29,079 $5,500 $12,269
189,294
kWh
$1,861
-
kW-mo/yr
$508 $222
-
MMBtu
$14,219
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs