ITAC Assessment: UD0906
ITAC logo
ITAC Assessment: UD0906
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Sealants, coatings and adhesives
NAICS 336991: Motorcycle, Bicycle, and Parts Manufacturing
SIC 2891: Adhesives and Sealants
Sales Range $50
M
to 100
M
# of Employees 130
Plant Area 75,000
ft2
Annual Production 59,000,000
lb
Production Hrs. Annual 6,500
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $68,780 2,021,641
kWh
Electricity Demand $120,006 7,560
kW-mo/yr
Natural Gas $25,594 3,788
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $91,662 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,277

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $17,248 - - $17,248
-
kW-mo/yr
- - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,093 - $501
14,148
kWh
$2,592
-
kW-mo/yr
- - -
03 2.7224: Reduce space conditioning during non-working hours $1,503 - $292
8,231
kWh
- $1,211
-
MMBtu
- -
04 2.7135: Install occupancy sensors $2,954 $1,575 $1,868
57,732
kWh
$494
-
kW-mo/yr
- $592 -
05 2.2628: Utilize a less expensive cooling method $5,162 $10,000 $3,198
90,288
kWh
$1,964
-
kW-mo/yr
- - -
06 2.2437: Recover waste heat from equipment $1,456 $5,614 - - $1,456
-
MMBtu
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,271 $1,000 $682
19,266
kWh
$589
-
kW-mo/yr
- - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $618 - $332
9,360
kWh
$286
-
kW-mo/yr
- - -
09 3.5315: Lease / purchase baler; sell cardboard to recycler $58,357 $14,000 $(-174.0)
(-4,914)
kWh
$(-1,906.0)
-
kW-mo/yr
- - $60,437
TOTAL RECOMMENDED $91,662 $32,189 $6,699
194,111
kWh
$21,267
-
kW-mo/yr
$2,667
-
MMBtu
$592 $60,437
TOTAL IMPLEMENTED $10,277 $8,189 $3,343
99,377
kWh
$3,675
-
kW-mo/yr
$2,667
-
MMBtu
$592 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs