| Assessment Year | 2014 |
|---|---|
| Principal Product | Bakery Equipment |
| NAICS | 333241: Food Product Machinery Manufacturing |
| SIC | 3556: Food Products Machinery |
| Sales Range | $10 M to 50M |
| # of Employees | 104 |
| Plant Area |
150,000
ft2
|
| Annual Production | 150
units
|
| Production Hrs. Annual | 2,860
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $58,043 | 1,018,705 |
kWh
|
$0.057 |
| Electricity Demand | $17,139 | 3,636 |
kW-mo/yr
|
$4.71 |
| Electricity Fees | $192 | - |
|
- |
| Natural Gas | $52,741 | 5,765 |
MMBtu
|
$9.15 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $45,284 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $29,461 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7314: Reduce ventilation air | $27,790 | $9,213 | - | - |
$27,790
-
MMBtu
|
- | |
| 02 | 2.7224: Reduce space conditioning during non-working hours | $14,091 | $200 | - | - |
$14,091
-
MMBtu
|
- | |
| 03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $540 | $1,500 | - | - |
$540
-
MMBtu
|
- | |
| 04 | 2.7135: Install occupancy sensors | $698 | $170 |
$579
10,270
kWh
|
$101
-
kW-mo/yr
|
- | $18 | |
| 05 | 2.7135: Install occupancy sensors | $583 | $210 |
$479
8,498
kWh
|
$84
-
kW-mo/yr
|
- | $20 | |
| 06 | 2.7135: Install occupancy sensors | $119 | $20 |
$119
2,105
kWh
|
- | - | - | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $566 | - |
$419
7,436
kWh
|
$147
-
kW-mo/yr
|
- | - | |
| 08 | 2.2437: Recover waste heat from equipment | $565 | $2,500 |
$(-31.0)
(-556)
kWh
|
$(-11.0)
-
kW-mo/yr
|
$607
-
MMBtu
|
- | |
| 09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $332 | - |
$246
4,358
kWh
|
$86
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $45,284 | $13,813 |
$1,811
32,111
kWh
|
$407
-
kW-mo/yr
|
$43,028
-
MMBtu
|
$38 | ||
| TOTAL IMPLEMENTED | $29,461 | $13,213 |
$388
6,880
kWh
|
$136
-
kW-mo/yr
|
$28,937
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs