Assessment Year | 2014 |
---|---|
Principal Product | meat products |
NAICS | 311611: Animal (except Poultry) Slaughtering |
SIC | 2011: Meat Packing Plants |
Sales Range | $10 M to 50M |
# of Employees | 35 |
Plant Area |
34,119
ft2
|
Annual Production | 7,000,000
lb
|
Production Hrs. Annual | 4,400
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $169,180 | 2,356,920 |
kWh
|
$0.072 |
Electricity Demand | $30,033 | 5,196 |
kW-mo/yr
|
$5.78 |
Electricity Fees | $32,115 | - |
|
- |
Natural Gas | $14,294 | 2,869 |
MMBtu
|
$4.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,166 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,735 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $1,057 | - |
$1,057
14,712
kWh
|
- | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $388 | - |
$312
4,347
kWh
|
$76
-
kW-mo/yr
|
- | - | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $85 | - | - | - |
$85
-
MMBtu
|
- | |
04 | 2.2621: Modify refrigeration system to operate at a lower pressure | $4,795 | $4,550 |
$4,795
66,714
kWh
|
- | - | - | |
05 | 2.2696: Use excess cold process fluid for industrial cooling needs | $2,075 | - |
$2,075
28,872
kWh
|
- | - | - | |
06 | 2.2621: Modify refrigeration system to operate at a lower pressure | $1,303 | - |
$1,303
18,137
kWh
|
- | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,350 | $7,126 |
$8,347
116,138
kWh
|
$1,003
-
kW-mo/yr
|
- | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $969 | $2,127 |
$873
12,149
kWh
|
$96
-
kW-mo/yr
|
- | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,254 | $15,180 |
$6,574
91,476
kWh
|
$1,373
-
kW-mo/yr
|
- | $(-2,693.0) | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,255 | $5,850 |
$2,394
33,306
kWh
|
$876
-
kW-mo/yr
|
- | $(-15.0) | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,635 | $3,920 |
$2,231
31,046
kWh
|
$466
-
kW-mo/yr
|
- | $(-62.0) | |
TOTAL RECOMMENDED | $31,166 | $38,753 |
$29,961
416,897
kWh
|
$3,890
-
kW-mo/yr
|
$85
-
MMBtu
|
$(-2,770.0) | ||
TOTAL IMPLEMENTED | $4,735 | $2,127 |
$4,563
63,505
kWh
|
$172
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs