Assessment Year | 2014 |
---|---|
Principal Product | Coatings/ Asphalt |
NAICS | 325510: Paint and Coating Manufacturing |
SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
Sales Range | $50 M to 100M |
# of Employees | 26 |
Plant Area |
50,000
ft2
|
Annual Production | 5,000
Tgal
|
Production Hrs. Annual | 3,300
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $98,645 | 1,473,862 |
kWh
|
$0.067 |
Electricity Demand | $44,942 | 5,148 |
kW-mo/yr
|
$8.73 |
Natural Gas | $46,173 | 8,958 |
MMBtu
|
$5.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,992 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,143 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $156 | $50 |
$126
1,878
kWh
|
$30
-
kW-mo/yr
|
- | - | |
02 | 2.7224: Reduce space conditioning during non-working hours | $11,196 | $300 | - | - |
$11,196
-
MMBtu
|
- | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $778 | - | - | - |
$778
-
MMBtu
|
- | |
04 | 2.2514: Cover open tanks | $57 | $200 | - | - |
$57
-
MMBtu
|
- | |
05 | 2.4113: Install motor voltage controller on lightly loaded motors | $8,127 | $6,567 |
$4,546
67,916
kWh
|
$1,423
-
kW-mo/yr
|
$2,158
-
MMBtu
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,748 | $2,320 |
$1,108
16,554
kWh
|
$482
-
kW-mo/yr
|
- | $158 | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $621 | $20 |
$621
9,282
kWh
|
- | - | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $309 | - |
$517
7,718
kWh
|
$92
-
kW-mo/yr
|
- | $(-300.0) | |
TOTAL RECOMMENDED | $22,992 | $9,457 |
$6,918
103,348
kWh
|
$2,027
-
kW-mo/yr
|
$14,189
-
MMBtu
|
$(-142.0) | ||
TOTAL IMPLEMENTED | $1,143 | $270 |
$1,264
18,878
kWh
|
$122
-
kW-mo/yr
|
$57
-
MMBtu
|
$(-300.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs