| Assessment Year | 2013 |
|---|---|
| Principal Product | Wind Turbine Towers |
| NAICS | 332312: Fabricated Structural Metal Manufacturing |
| SIC | 3441: Fabricated Structural Metal |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
99,350
ft2
|
| Annual Production | 55
units
|
| Production Hrs. Annual | 6,200
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $187,392 | 3,726,720 |
kWh
|
$0.050 |
| Electricity Demand | $139,878 | 8,952 |
kW-mo/yr
|
$15.63 |
| Electricity Fees | $11,549 | - |
|
- |
| Natural Gas | $26,299 | 4,617 |
MMBtu
|
$5.70 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $146,235 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,532 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4226: Use / purchase optimum sized compressor | $112,427 | $100,000 |
$81,040
1,611,792
kWh
|
$31,387
-
kW-mo/yr
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,664 | $3,000 |
$340
6,772
kWh
|
$8,324
-
kW-mo/yr
|
- | - | |
| 03 | 2.2437: Recover waste heat from equipment | $8,643 | $30,000 |
$(-84.0)
(-1,679)
kWh
|
$(-33.0)
-
kW-mo/yr
|
$8,760
-
MMBtu
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $868 | $1,000 |
$624
12,416
kWh
|
$244
-
kW-mo/yr
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,992 | $27,380 |
$10,195
202,758
kWh
|
$5,096
-
kW-mo/yr
|
- | $(-299.0) | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $641 | $300 |
$641
12,742
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $146,235 | $161,680 |
$92,756
1,844,801
kWh
|
$45,018
-
kW-mo/yr
|
$8,760
-
MMBtu
|
$(-299.0) | ||
| TOTAL IMPLEMENTED | $9,532 | $4,000 |
$964
19,188
kWh
|
$8,568
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs