ITAC Assessment: UD0891
ITAC logo
ITAC Assessment: UD0891
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Wind Turbine Towers
NAICS 332312: Fabricated Structural Metal Manufacturing
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 99,350
ft2
Annual Production 55
units
Production Hrs. Annual 6,200
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $187,392 3,726,720
kWh
Electricity Demand $139,878 8,952
kW-mo/yr
Electricity Fees $11,549 -
Natural Gas $26,299 4,617
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $146,235 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,532

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.4226: Use / purchase optimum sized compressor $112,427 $100,000 $81,040
1,611,792
kWh
$31,387
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,664 $3,000 $340
6,772
kWh
$8,324
-
kW-mo/yr
- -
03 2.2437: Recover waste heat from equipment $8,643 $30,000 $(-84.0)
(-1,679)
kWh
$(-33.0)
-
kW-mo/yr
$8,760
-
MMBtu
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $868 $1,000 $624
12,416
kWh
$244
-
kW-mo/yr
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $14,992 $27,380 $10,195
202,758
kWh
$5,096
-
kW-mo/yr
- $(-299.0)
06 2.7142: Utilize higher efficiency lamps and/or ballasts $641 $300 $641
12,742
kWh
- - -
TOTAL RECOMMENDED $146,235 $161,680 $92,756
1,844,801
kWh
$45,018
-
kW-mo/yr
$8,760
-
MMBtu
$(-299.0)
TOTAL IMPLEMENTED $9,532 $4,000 $964
19,188
kWh
$8,568
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs