ITAC Assessment: UD0880
ITAC logo
ITAC Assessment: UD0880
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Bacon, Meatballs
NAICS 311613: Rendering and Meat Byproduct Processing
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range $100
M
to 500
M
# of Employees 400
Plant Area 117,000
ft2
Annual Production 57,500,000
lb
Production Hrs. Annual 7,344
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,015,991 14,993,944
kWh
Electricity Demand $125,571 26,472
kW-mo/yr
Natural Gas $554,744 129,035
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $202,265 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $164,712

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Personnel Changes Savings
01 2.3511: Use plant owned transformers or lease transformers $37,553 $100,000 - - $42,553 - - - $(-5,000.0)
02 3.4116: Meter recycled water (to reduce sewer charges) $5,784 $5,000 - - - - $5,784
-
Tgal
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $14,581 $15,000 $13,009
201,130
kWh
$1,298
-
kW-mo/yr
- - - - $274
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,196 $3,400 $1,156
17,870
kWh
- - - - - $40
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $6,656 - $6,029
93,207
kWh
$627
-
kW-mo/yr
- - - - -
06 2.4224: Upgrade controls on compressors $12,462 - $11,332
175,200
kWh
$1,130
-
kW-mo/yr
- - - - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,120 $1,000 $3,019
46,678
kWh
$301
-
kW-mo/yr
- - - - $(-1,200.0)
08 2.1241: Reduce excessive boiler blowdown $35,463 $15,000 - - - $18,344
-
MMBtu
$10,710
-
Tgal
$6,409
-
gal
-
09 2.2136: Install / repair insulation on steam lines $25,120 $4,600 - - - $25,120
-
MMBtu
- - -
10 2.2414: Use waste heat from hot flue gases to preheat $23,091 $25,000 - - - $23,091
-
MMBtu
- - -
11 2.1233: Analyze flue gas for proper air/fuel ratio $3,315 $8,000 - - - $3,315
-
MMBtu
- - -
12 2.1233: Analyze flue gas for proper air/fuel ratio $7,170 $8,000 - - - $7,170
-
MMBtu
- - -
13 2.2511: Insulate bare equipment $3,572 $1,221 - - - $3,572
-
MMBtu
- - -
14 2.2621: Modify refrigeration system to operate at a lower pressure $17,352 - $17,352
268,904
kWh
- - - - - -
15 2.2696: Use excess cold process fluid for industrial cooling needs $6,830 - $6,830
105,592
kWh
- - - - - -
TOTAL RECOMMENDED $202,265 $186,221 $58,727
908,581
kWh
$3,356
-
kW-mo/yr
$42,553 $80,612
-
MMBtu
$16,494
-
Tgal
$6,409
-
gal
$(-5,886.0)
TOTAL IMPLEMENTED $164,712 $86,221 $58,727
908,581
kWh
$3,356
-
kW-mo/yr
- $80,612
-
MMBtu
$16,494
-
Tgal
$6,409
-
gal
$(-886.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs