ITAC Assessment: UD0874
ITAC logo
ITAC Assessment: UD0874
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Flavors
NAICS 311930: Flavoring Syrup and Concentrate Manufacturing
SIC 2087: Flavoring Extracts and Flavoring Syrups, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 300
Plant Area 187,515
ft2
Annual Production 17,087,000
ton
Production Hrs. Annual 8,760
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $494,149 15,390,145
kWh
Electricity Demand $440,559 26,844
kW-mo/yr
Natural Gas $1,085,083 206,198
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $544,187 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,935

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 2.3212: Optimize plant power factor $23,112 $20,000 - - $23,112 - - -
02 3.4114: Replace city water with recycled water via cooling tower $16,400 $200 - - - - $16,400
-
Tgal
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $6,108 $38,600 $3,441
244,177
kWh
$1,830
-
kW-mo/yr
- - - $837
04 2.7142: Utilize higher efficiency lamps and/or ballasts $8,148 $51,240 $4,101
133,568
kWh
$2,948
-
kW-mo/yr
- - - $1,099
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,338 $6,405 $713
23,207
kWh
$450
-
kW-mo/yr
- - - $175
06 2.4131: Size electric motors for peak operating efficiency $95,537 $39,093 $17,097
556,891
kWh
$18,457
-
kW-mo/yr
- $59,983
-
MMBtu
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,535 - $2,173
70,795
kWh
$1,562
-
kW-mo/yr
- - - $(-1,200.0)
08 2.1221: Replace obsolete burners with more efficient ones $58,058 $88,200 - - - $58,058
-
MMBtu
- -
09 2.1233: Analyze flue gas for proper air/fuel ratio $4,928 $12,300 - - - $4,928
-
MMBtu
- -
10 2.7232: Replace existing hvac unit with high efficiency model $10,382 $30,000 - - - $10,382
-
MMBtu
- -
11 2.3416: Use combined cycle gas turbine generator sets with waste heat boilers connected to turbine exhaust $317,641 $906,381 $299,859
9,767,400
kWh
$215,552
-
kW-mo/yr
- $(-91,305.0)
-
MMBtu
- $(-106,465.0)
TOTAL RECOMMENDED $544,187 $1,192,419 $327,384
10,796,038
kWh
$240,799
-
kW-mo/yr
$23,112 $42,046
-
MMBtu
$16,400
-
Tgal
$(-105,554.0)
TOTAL IMPLEMENTED $18,935 $200 $2,173
70,795
kWh
$1,562
-
kW-mo/yr
- - $16,400
-
Tgal
$(-1,200.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs