Assessment Year | 2012 |
---|---|
Principal Product | Flexible Projection Material |
NAICS | 325992: Photographic Film, Paper, Plate, and Chemical Manufacturing |
SIC | 3861: Photographic Equipment and Supplies |
Sales Range | $1 M to 5M |
# of Employees | 27 |
Plant Area |
43,000
ft2
|
Annual Production | 9,000
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $121,850 | 2,662,507 |
kWh
|
$0.046 |
Electricity Demand | $111,979 | 6,984 |
kW-mo/yr
|
$16.03 |
Natural Gas | $72,539 | 10,990 |
MMBtu
|
$6.60 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $42,426 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,693 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7134: Use photocell controls | $1,385 | $1,660 |
$422
9,379
kWh
|
$963
-
kW-mo/yr
|
- | |
02 | 2.4224: Upgrade controls on compressors | $5,228 | $10,000 |
$5,228
116,184
kWh
|
- | - | |
03 | 2.4226: Use / purchase optimum sized compressor | $4,564 | $16,800 |
$4,564
101,430
kWh
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $3,610 | $1,500 | - | - |
$3,610
-
MMBtu
|
|
05 | 2.4221: Install compressor air intakes in coolest locations | $1,199 | $1,500 |
$810
17,722
kWh
|
$389
-
kW-mo/yr
|
- | |
06 | 2.2113: Repair or replace steam traps | $10,454 | $1,800 | - | - |
$10,454
-
MMBtu
|
|
07 | 2.2163: Use minimum steam operating pressure | $7,517 | - | - | - |
$7,517
-
MMBtu
|
|
08 | 2.2437: Recover waste heat from equipment | $2,567 | $4,000 |
$1,529
33,969
kWh
|
$1,038
-
kW-mo/yr
|
- | |
09 | 2.2522: Isolate hot or cold equipment | $1,602 | $4,000 |
$1,602
35,604
kWh
|
- | - | |
10 | 2.2511: Insulate bare equipment | $1,512 | - |
$1,512
33,617
kWh
|
- | - | |
11 | 2.7224: Reduce space conditioning during non-working hours | $2,788 | $3,000 | - | - |
$2,788
-
MMBtu
|
|
TOTAL RECOMMENDED | $42,426 | $44,260 |
$15,667
347,905
kWh
|
$2,390
-
kW-mo/yr
|
$24,369
-
MMBtu
|
||
TOTAL IMPLEMENTED | $33,693 | $19,460 |
$7,972
176,902
kWh
|
$1,352
-
kW-mo/yr
|
$24,369
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs