ITAC Assessment: UD0867
ITAC logo
ITAC Assessment: UD0867
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Plastic Bottles
NAICS 326160: Plastics Bottle Manufacturing
SIC 3085: Plastics Bottles
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 240,820
ft2
Annual Production 92,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $737,651 16,869,600
kWh
Electricity Demand $607,572 34,152
kW-mo/yr
Electricity Fees $1,481 -
Natural Gas $61,119 8,848
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $134,468 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $61,750

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $20,897 $12,947 $11,942
273,276
kWh
$8,666
-
kW-mo/yr
$289
02 2.7142: Utilize higher efficiency lamps and/or ballasts $17,726 $35,503 $10,049
229,949
kWh
$7,292
-
kW-mo/yr
$385
03 2.7142: Utilize higher efficiency lamps and/or ballasts $6,088 $10,618 $3,926
89,845
kWh
$1,820
-
kW-mo/yr
$342
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $8,831 - $4,868
111,388
kWh
$3,963
-
kW-mo/yr
-
05 2.4131: Size electric motors for peak operating efficiency $20,787 $15,000 $11,659
266,802
kWh
$9,128
-
kW-mo/yr
-
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $15,942 $1,000 $7,143
163,472
kWh
$9,399
-
kW-mo/yr
$(-600.0)
07 2.4239: Eliminate or reduce compressed air usage $10,916 - $4,451
101,839
kWh
$6,465
-
kW-mo/yr
-
08 2.4221: Install compressor air intakes in coolest locations $8,474 $10,000 $4,059
92,885
kWh
$4,415
-
kW-mo/yr
-
09 2.2628: Utilize a less expensive cooling method $23,710 - $13,294
304,200
kWh
$10,416
-
kW-mo/yr
-
10 2.2628: Utilize a less expensive cooling method $1,097 - $1,097
25,114
kWh
- -
TOTAL RECOMMENDED $134,468 $85,068 $72,488
1,658,770
kWh
$61,564
-
kW-mo/yr
$416
TOTAL IMPLEMENTED $61,750 $60,068 $34,157
781,656
kWh
$27,177
-
kW-mo/yr
$416
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs