ITAC Assessment: UD0858
ITAC logo
ITAC Assessment: UD0858
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Metal Fabrication
NAICS 332119: Metal Crown, Closure, and Other Metal Stamping (except Automotive)
SIC 3469: Metal Stampings, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 45
Plant Area 53,000
ft2
Annual Production 10,000,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $93,318 1,813,728
kWh
Electricity Demand $59,663 4,548
kW-mo/yr
Natural Gas $4,827 521
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,259 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,016

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $7,297 $12,425 $3,928
79,107
kWh
$3,313
-
kW-mo/yr
$56
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,138 $3,850 $1,152
23,190
kWh
$971
-
kW-mo/yr
$15
03 2.4239: Eliminate or reduce compressed air usage $1,006 $500 $546
10,986
kWh
$460
-
kW-mo/yr
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,010 $1,000 $548
11,041
kWh
$462
-
kW-mo/yr
-
05 2.4239: Eliminate or reduce compressed air usage $399 $300 $216
4,359
kWh
$183
-
kW-mo/yr
-
06 2.7224: Reduce space conditioning during non-working hours $409 $360 $409
8,244
kWh
- -
TOTAL RECOMMENDED $12,259 $18,435 $6,799
136,927
kWh
$5,389
-
kW-mo/yr
$71
TOTAL IMPLEMENTED $2,016 $1,500 $1,094
22,027
kWh
$922
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs