ITAC Assessment: UD0839
ITAC logo
ITAC Assessment: UD0839
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Packaged Food
NAICS 311422: Specialty Canning
SIC 2032: Canned Specialties
Sales Range $100
M
to 500
M
# of Employees 365
Plant Area 182,000
ft2
Annual Production 125,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $837,216 12,255,959
kWh
Electricity Demand $118,893 24,611
kW-mo/yr
Natural Gas $616,722 96,888
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $370,062 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $166,403

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,985 $5,668 $3,549
57,250
kWh
$459
-
kW-mo/yr
- - $977 - - -
02 2.7135: Install occupancy sensors $1,620 $1,875 $1,517
22,810
kWh
- - - $103 - - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $58,395 $500 $27,011
435,664
kWh
$2,632
-
kW-mo/yr
- - $(-300.0) - $29,052 -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $20,472 - $13,321
214,848
kWh
- - - $(-625.0) - $7,776 -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,623 $5,000 $6,380
102,899
kWh
$1,243
-
kW-mo/yr
- - - - - -
06 2.2441: Preheat boiler makeup water with waste process heat $80,401 $90,000 - - $27,901
-
MMBtu
- - $52,500 - -
07 2.2128: Use steam condensate for hot water supply (non-potable) $29,882 $59,764 - - $28,593
-
MMBtu
- - - - $1,289
-
Tgal
08 2.1221: Replace obsolete burners with more efficient ones $80,401 $90,000 - - $27,901
-
MMBtu
- - - $52,500 -
09 2.1233: Analyze flue gas for proper air/fuel ratio $14,418 $3,000 - - $14,418
-
MMBtu
- - - - -
10 2.1212: Operate boilers on high fire setting $11,810 $23,620 - - $11,810
-
MMBtu
- - - - -
11 2.2135: Repair and eliminate steam leaks $5,425 $2,100 - - $5,271
-
MMBtu
- - - - $154
-
Tgal
12 2.2122: Install / repair insulation on condensate lines $1,987 $993 - - $1,987
-
MMBtu
- - - - -
13 3.4111: Use closed cycle process to minimize waste water production $48,911 $75,000 $(-7,078.0)
(-114,154)
kWh
$(-1,103.0)
-
kW-mo/yr
- $38,098
-
Tgal
- - - $18,994
-
Tgal
14 2.7235: Install fossil fuel make-up air unit $3,732 $25 - - $3,732
-
MMBtu
- - - - -
TOTAL RECOMMENDED $370,062 $357,545 $44,700
719,317
kWh
$3,231
-
kW-mo/yr
$121,613
-
MMBtu
$38,098
-
Tgal
$155 $52,500 $89,328 $20,437
-
Tgal
TOTAL IMPLEMENTED $166,403 $110,881 $36,803
593,608
kWh
$1,988
-
kW-mo/yr
$33,486
-
MMBtu
$38,098
-
Tgal
$52 - $36,828 $19,148
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs