Assessment Year | 2011 |
---|---|
Principal Product | Gray and Ductile Castings |
NAICS | 331511: Iron Foundries |
SIC | 3321: Gray and Ductile Iron Foundries |
Sales Range | $1 M to 5M |
# of Employees | 20 |
Plant Area |
40,000
ft2
|
Annual Production | 1,100
ton
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $48,815 | 549,455 |
kWh
|
$0.089 |
Electricity Demand | $28,748 | 614 |
kW-mo/yr
|
$46.82 |
Electricity Fees | $4,964 | - |
|
- |
Natural Gas | $26,565 | 2,225 |
MMBtu
|
$11.94 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,364 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,398 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $688 | $3,315 |
$519
6,024
kWh
|
$137
-
kW-mo/yr
|
- | $32 | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $251 | $860 |
$185
2,153
kWh
|
$49
-
kW-mo/yr
|
- | $17 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $197 | $665 |
$158
1,835
kWh
|
$42
-
kW-mo/yr
|
- | $(-3.0) | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $408 | $25 |
$323
3,750
kWh
|
$85
-
kW-mo/yr
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $211 | $25 |
$167
1,935
kWh
|
$44
-
kW-mo/yr
|
- | - | |
06 | 2.6242: Minimize operation of equipment maintained in standby condition | $3,027 | $6,500 |
$2,624
30,472
kWh
|
$403
-
kW-mo/yr
|
- | - | |
07 | 2.7231: Use radiant heater for spot heating | $6,582 | $2,349 | - | - |
$6,582
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $11,364 | $13,739 |
$3,976
46,169
kWh
|
$760
-
kW-mo/yr
|
$6,582
-
MMBtu
|
$46 | ||
TOTAL IMPLEMENTED | $7,398 | $3,064 |
$648
7,520
kWh
|
$171
-
kW-mo/yr
|
$6,582
-
MMBtu
|
$(-3.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs