ITAC Assessment: UD0824
ITAC logo
ITAC Assessment: UD0824
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product gray and ductile castings
NAICS 331511: Iron Foundries
SIC 3321: Gray and Ductile Iron Foundries
Sales Range $50
M
to 100
M
# of Employees 300
Plant Area 463,000
ft2
Annual Production 29,974
ton
Production Hrs. Annual 2,640
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,601,455 40,287,654
kWh
Electricity Demand $900,818 11,722
kW-mo/yr
Natural Gas $453,649 46,221
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,933,865 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Water Consumption Savings
01 2.3192: Use fossil fuel powered generator during peak demand periods $48,864 $143,000 - - $48,864 - - -
02 2.9121: Install wind powered electric generator $1,443,350 $3,000,000 $1,443,350
5,281,037
kWh
- - - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $8,706 $15,238 $7,239
136,322
kWh
$2,349
-
kW-mo/yr
- - $(-882.0) -
04 2.7121: Utilize daylight whenever possible in lieu of artificial light $8,478 $10,195 $8,478
159,662
kWh
- - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $11,762 $6,380 $6,154
98,963
kWh
$5,255
-
kW-mo/yr
- - $353 -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $4,468 $4,640 $3,727
70,182
kWh
$654
-
kW-mo/yr
- - $87 -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,897 $20 $1,696
31,944
kWh
$1,201
-
kW-mo/yr
- - - -
08 2.4224: Upgrade controls on compressors $81,554 $20,000 $70,317
1,324,210
kWh
$11,237
-
kW-mo/yr
- - - -
09 2.4231: Reduce the pressure of compressed air to the minimum required $49,948 $16,000 $37,712
710,208
kWh
$12,236
-
kW-mo/yr
- - - -
10 2.4221: Install compressor air intakes in coolest locations $14,595 $1,500 $10,705
201,600
kWh
$3,890
-
kW-mo/yr
- - - -
11 2.4239: Eliminate or reduce compressed air usage $14,160 $2,000 $14,160
266,667
kWh
- - - - -
12 2.4322: Use or replace with energy efficient substitutes $486 $540 $367
6,912
kWh
$119
-
kW-mo/yr
- - - -
13 2.2514: Cover open tanks $80,740 $1,600 $80,740
1,523,405
kWh
- - - - -
14 2.2511: Insulate bare equipment $61,285 $5,152 $61,285
1,156,320
kWh
- - - - -
15 2.2314: Replace heat treating oven with more efficient unit $43,001 $1,243,001 - - - $43,001
-
MMBtu
- -
16 2.1123: Install automatic stack damper $22,399 $500 - - - $22,399
-
MMBtu
- -
17 2.2514: Cover open tanks $8,613 $17,226 - - - $8,613
-
MMBtu
- -
18 2.2694: Use highest temperature for chilling or cold storage $18,106 $36,212 - - - - - $18,106
-
Tgal
19 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,081 $11,700 $6,081
114,514
kWh
- - - - -
20 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,372 $11,000 $4,372
82,336
kWh
- - - - -
TOTAL RECOMMENDED $1,933,865 $4,545,904 $1,756,383
11,164,282
kWh
$36,941
-
kW-mo/yr
$48,864 $74,013
-
MMBtu
$(-442.0) $18,106
-
Tgal
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs