ITAC Assessment: UD0802
ITAC logo
ITAC Assessment: UD0802
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Sheet Metal Fabrication and Machined Parts
NAICS 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range less than $500
k
# of Employees 35
Plant Area 80,000
ft2
Annual Production 3,750
pieces
Production Hrs. Annual 2,250
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $103,166 983,640
kWh
Natural Gas $70,531 6,330
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,575 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,877

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7491: Insulate glazing, walls, ceilings, and roofs $13,072 $16,185 $1,391
14,195
kWh
- $11,681
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $8,384 $29,087 $6,726
64,916
kWh
$1,658
-
kW-mo/yr
-
03 2.7224: Reduce space conditioning during non-working hours $7,645 - $3,900
39,800
kWh
- $3,745
-
MMBtu
04 2.1123: Install automatic stack damper $3,637 $1,000 - - $3,637
-
MMBtu
05 2.7121: Utilize daylight whenever possible in lieu of artificial light $1,711 $6,468 $1,711
17,463
kWh
- -
06 2.2437: Recover waste heat from equipment $1,230 $1,500 - - $1,230
-
MMBtu
07 2.2443: Re-use or recycle hot or cold process exhaust air $1,084 $2,812 - - $1,084
-
MMBtu
08 2.7142: Utilize higher efficiency lamps and/or ballasts $797 $1,907 $621
6,338
kWh
$176
-
kW-mo/yr
-
09 2.7142: Utilize higher efficiency lamps and/or ballasts $487 $2,374 $372
3,794
kWh
$115
-
kW-mo/yr
-
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,334 $1,000 $1,058
10,800
kWh
$276
-
kW-mo/yr
-
11 2.4231: Reduce the pressure of compressed air to the minimum required $194 - $154
1,575
kWh
$40
-
kW-mo/yr
-
TOTAL RECOMMENDED $39,575 $62,333 $15,933
158,881
kWh
$2,265
-
kW-mo/yr
$21,377
-
MMBtu
TOTAL IMPLEMENTED $19,877 $35,868 $12,677
125,648
kWh
$2,225
-
kW-mo/yr
$4,975
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs