| Assessment Year | 2024 | 
|---|---|
| Principal Product | School students | 
| NAICS | 611110: Elementary and Secondary Schools | 
| SIC | 8211: Elementary and Secondary Schools | 
| Sales Range | $1 Mto 5 M | 
| # of Employees | 34 | 
| Plant Area | 57,033 
ft2
 | 
| Annual Production | 110 
units
 | 
| Production Hrs. Annual | 3,377 
hrs
 | 
| Location (State) | Texas | 
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $34,927 | 735,296 | 
kWh
 | $0.048 | 
| Electricity Demand | $48,205 | 3,636 | 
kW-mo/yr
 | $13.26 | 
| Natural Gas | $5,831 | 528 | 
MMBtu
 | $11.04 | 
| TOTAL YEARLY COSTS | $88,963 | |||
| RECOMMENDED SAVINGS* | $30,944 | See individual recommendations below*Non-energy impacts included in savings. | ||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | 
|---|---|---|---|---|---|---|---|
| 01 | 2.5123: Reduce fluid flow rates | $1,310 | $3,000 | $1,310 27,570
                                 
kWh
 | - | - | |
| 02 | 2.9114: Use solar heat to make electricty | $25,377 | $489,840 | $20,565 432,950
                                 
kWh
 | $4,812 -
                                 
kW-mo/yr
 | - | |
| 03 | 2.1132: Repair faulty louvers and dampers | $412 | $3,000 | $14 300
                                 
kWh
 | - | $398 -
                                 
MMBtu
 | |
| 04 | 2.7135: Install occupancy sensors | $2,244 | $1,215 | $520 10,941
                                 
kWh
 | $1,724 -
                                 
kW-mo/yr
 | - | |
| 05 | 2.2625: Chill water to the highest temperature possible | $1,601 | $3,000 | $201 4,227
                                 
kWh
 | - | $1,400 -
                                 
MMBtu
 | |
| TOTAL RECOMMENDED | $30,944 | $500,055 | $22,610 475,988
                                 
kWh
 | $6,536 -
                                 
kW-mo/yr
 | $1,798 -
                                 
MMBtu
 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs
             
             
             
            