Assessment Year | 2009 |
---|---|
Principal Product | chrome wheels |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $1 M to 5M |
# of Employees | 35 |
Plant Area |
145,000
ft2
|
Annual Production | 12,000
pieces
|
Production Hrs. Annual | 2,300
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $41,965 | 1,012,200 |
kWh
|
$0.041 |
Electricity Demand | $68,468 | 407 |
kW-mo/yr
|
$168.23 |
Natural Gas | $94,996 | 7,293 |
MMBtu
|
$13.03 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $42,179 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,795 | $20,953 |
$3,377
84,415
kWh
|
$6,430
-
kW-mo/yr
|
- | - | $(-12.0) | - | |
02 | 3.4153: Use counter current rinsing to reduce waste water | $6,223 | $1,500 | - | - | - |
$3,051
-
MMBtu
|
- |
$3,172
-
Tgal
|
|
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $6,189 | $100 | - | - | - |
$6,189
-
MMBtu
|
- | - | |
04 | 2.2135: Repair and eliminate steam leaks | $6,163 | $2,000 | - | - | - |
$6,163
-
MMBtu
|
- | - | |
05 | 2.2514: Cover open tanks | $4,422 | $360 | - | - | - |
$7,297
-
MMBtu
|
$(-2,875.0) | - | |
06 | 2.2136: Install / repair insulation on steam lines | $2,259 | $1,152 | - | - | - |
$2,259
-
MMBtu
|
- | - | |
07 | 2.7124: Make a practice of turning off lights when not needed | $1,870 | - |
$644
16,100
kWh
|
$1,226
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,628 | $5,700 |
$1,089
27,232
kWh
|
$1,069
-
kW-mo/yr
|
- | - | $(-530.0) | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,539 | $4,298 |
$533
13,324
kWh
|
$1,015
-
kW-mo/yr
|
- | - | $(-9.0) | - | |
10 | 2.8123: Pay utility bills on time | $1,095 | - | - | - | $1,095 | - | - | - | |
11 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $546 | $551 |
$57
1,417
kWh
|
$489
-
kW-mo/yr
|
- | - | - | - | |
12 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $450 | - |
$165
4,122
kWh
|
$285
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $42,179 | $36,614 |
$5,865
146,610
kWh
|
$10,514
-
kW-mo/yr
|
$1,095 |
$24,959
-
MMBtu
|
$(-3,426.0) |
$3,172
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs