Assessment Year | 2009 |
---|---|
Principal Product | Polymer and Material Handling and Storage Equipment |
NAICS | 326121: Unlaminated Plastics Profile Shape Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 120 |
Plant Area |
150,000
ft2
|
Annual Production | 6,600,000
lb
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $233,951 | 8,316,000 |
kWh
|
$0.028 |
Electricity Demand | $215,955 | 18,528 |
kW-mo/yr
|
$11.66 |
Natural Gas | $175,285 | 17,454 |
MMBtu
|
$10.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,171,205 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.912: Wind power | $1,103,774 | $5,850,000 |
$1,103,774
11,439,132
kWh
|
- | - | - | - | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $24,846 | $92,500 |
$14,545
532,800
kWh
|
$10,301
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.6218: Turn off equipment when not in use | $13,922 | $4,000 |
$8,150
298,550
kWh
|
$5,772
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.2511: Insulate bare equipment | $12,029 | $2,640 |
$12,029
240,210
kWh
|
- | - | - | - | - | |
05 | 2.3212: Optimize plant power factor | $4,640 | $12,000 | - | - | $4,640 | - | - | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,270 | $8,700 |
$1,782
92,160
kWh
|
$2,488
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,350 | $1,000 |
$2,350
50,400
kWh
|
- | - | - | - | - | |
08 | 2.2511: Insulate bare equipment | $2,010 | $900 | - | - | - |
$2,010
-
MMBtu
|
- | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,247 | $1,000 |
$2,887
61,920
kWh
|
- | - | - | $(-1,440.0) | $(-200.0) | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,067 | $5,170 |
$622
23,040
kWh
|
$445
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $1,050 | - |
$612
22,680
kWh
|
$438
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $1,171,205 | $5,977,910 |
$1,146,751
12,760,892
kWh
|
$19,444
-
kW-mo/yr
|
$4,640 |
$2,010
-
MMBtu
|
$(-1,440.0) | $(-200.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs