ITAC Assessment: AT0059
ITAC logo
ITAC Assessment: AT0059
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product BATTERIES
NAICS
n/a
SIC 3691: Storage Batteries
Sales Range $10
M
to 50
M
# of Employees 450
Plant Area
n/a
Annual Production 2,000,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,043,881 21,919,989
kWh
Natural Gas $218,137 40,829
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $70,195 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,160

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $447 $612 $447
9,379
kWh
- -
02 3.1192: Reduce scrap production $3,755 $2,000 $3,755
78,839
kWh
- -
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $26,952 $10,000 $50,019
1,050,117
kWh
$(-23,067.0)
-
MMBtu
-
04 2.2511: Insulate bare equipment $4,635 $500 - $4,635
-
MMBtu
-
05 2.2414: Use waste heat from hot flue gases to preheat $15,743 $12,000 - $15,743
-
MMBtu
-
06 2.7226: Use computer programs to optimize hvac performance $14,839 $5,000 $14,839
311,547
kWh
- -
07 2.2511: Insulate bare equipment $1,232 $500 - $1,232
-
MMBtu
-
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $586 - $586
12,309
kWh
- -
09 2.4312: Improve lubrication practices $2,006 - $2,806
58,910
kWh
- $(-800.0)
TOTAL RECOMMENDED $70,195 $30,612 $72,452
1,521,101
kWh
$(-1,457.0)
-
MMBtu
$(-800.0)
TOTAL IMPLEMENTED $33,160 $12,612 $57,027
1,197,245
kWh
$(-23,067.0)
-
MMBtu
$(-800.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs