Assessment Year | 2009 |
---|---|
Principal Product | Horticulture Containers |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 270 |
Plant Area |
310,000
ft2
|
Annual Production | 700,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,842,148 | 31,483,292 |
kWh
|
$0.059 |
Natural Gas | $153,875 | 14,252 |
MMBtu
|
$10.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $184,523 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $86,175 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $35,682 | $25,000 |
$35,682
584,963
kWh
|
- | - | - | - | |
02 | 2.6218: Turn off equipment when not in use | $33,134 | - |
$33,134
543,180
kWh
|
- | - | - | - | |
03 | 2.2511: Insulate bare equipment | $32,063 | $3,630 |
$32,063
538,740
kWh
|
- | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $30,092 | $46,620 |
$28,233
315,000
kWh
|
- | - | $1,859 | - | |
05 | 2.4224: Upgrade controls on compressors | $16,900 | $500 |
$16,900
277,056
kWh
|
- | - | - | - | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,888 | $26,100 |
$12,888
211,277
kWh
|
- | - | - | - | |
07 | 2.3212: Optimize plant power factor | $12,305 | $92,000 | - | $12,305 | - | - | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,410 | $20,400 |
$5,410
88,704
kWh
|
- | - | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,439 | $8,250 |
$3,634
59,658
kWh
|
- | - | - | $(-195.0) | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,610 | $1,000 |
$6,610
108,370
kWh
|
- | $(-3,600.0) | - | $(-400.0) | |
TOTAL RECOMMENDED | $184,523 | $223,500 |
$174,554
2,726,948
kWh
|
$12,305 | $(-3,600.0) | $1,859 | $(-595.0) | ||
TOTAL IMPLEMENTED | $86,175 | $56,370 |
$88,511
1,303,264
kWh
|
- | $(-3,600.0) | $1,859 | $(-595.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs