ITAC Assessment: UD0779
ITAC logo
ITAC Assessment: UD0779
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product refrigeration and sensor parts
NAICS 334419: Other Electronic Component Manufacturing
SIC 3679: Electronic Components, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 75,157
ft2
Annual Production 35,000,000
pieces
Production Hrs. Annual 6,336
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $612,001 8,013,240
kWh
Natural Gas $565,508 50,115
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $508,333 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $235,024

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Water Consumption Savings
01 2.1117: Relocate oven / furnace to more efficient location $255,168 $200,000 - - - $145,168
-
MMBtu
- $110,000 -
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $95,648 $1,000 $7,392
211,200
kWh
$88,256
-
kW-mo/yr
- - - - -
03 2.1224: Replace boiler $17,736 $65,000 - - - $17,736
-
MMBtu
- - -
04 3.1227: Use counter-current rinsing to reduce rinse water volume (gravure) $13,555 $500 - - - - - - $13,555
-
Tgal
05 2.2136: Install / repair insulation on steam lines $13,503 $3,318 - - - $13,503
-
MMBtu
- - -
06 2.1116: Improve combustion control capability $75,942 $100,000 - - - $75,942
-
MMBtu
- - -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,679 $35,000 $3,770
107,712
kWh
$3,909
-
kW-mo/yr
- - - - -
08 2.2511: Insulate bare equipment $8,895 $412 $4,369
124,819
kWh
$4,526
-
kW-mo/yr
- - - - -
09 2.3212: Optimize plant power factor $5,482 $3,000 - - $5,482 - - - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $4,499 $9,173 $1,634
46,696
kWh
$1,695
-
kW-mo/yr
- - $1,170 - -
11 4.821: Pay bills on time to avoid late fees $4,322 - - - - - - $4,322 -
12 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,658 $1,000 $1,796
51,320
kWh
$1,862
-
kW-mo/yr
- - - - -
13 2.2511: Insulate bare equipment $1,228 $100 - - - $1,228
-
MMBtu
- - -
14 2.2514: Cover open tanks $537 $360 - - - $537
-
MMBtu
- - -
15 2.2437: Recover waste heat from equipment $481 $2,000 - - - $481
-
MMBtu
- - -
TOTAL RECOMMENDED $508,333 $420,863 $18,961
541,747
kWh
$100,248
-
kW-mo/yr
$5,482 $254,595
-
MMBtu
$1,170 $114,322 $13,555
-
Tgal
TOTAL IMPLEMENTED $235,024 $171,690 $13,557
387,339
kWh
$94,644
-
kW-mo/yr
- $108,946
-
MMBtu
- $4,322 $13,555
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs