ITAC Assessment: UD0777
ITAC logo
ITAC Assessment: UD0777
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Brake Components
NAICS 327910: Abrasive Product Manufacturing
SIC 3291: Abrasive Products
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 100,000
ft2
Annual Production 100,000,000
pieces
Production Hrs. Annual 6,600
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $538,702 7,475,900
kWh
Natural Gas $549,243 68,813
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,454,462 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $189,799

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings Water Consumption Savings
01 4.131: Modify process to reduce material use/cost $621,360 $28,800 - - - $3,600
-
lb
$380,160 $237,600 - -
02 2.2191: Substitute hot process fluids for steam $468,137 $140,000 - - $468,137
-
MMBtu
- - - - -
03 3.8132: Use less toxic and volatile solvent substitutes $86,400 $85,000 - - - - $86,400 - - -
04 2.2223: Enhance sensitivity of temperature control and cutoff $70,469 $40,000 - - $70,469
-
MMBtu
- - - - -
05 3.4114: Replace city water with recycled water via cooling tower $45,421 $74,873 - - - - - - - $45,421
-
Tgal
06 2.2124: Install de-aerator in place of condensate tank $35,664 $50,000 - - $28,568
-
MMBtu
- - - $6,000 $1,096
-
Tgal
07 2.4131: Size electric motors for peak operating efficiency $35,347 $15,000 $29,733
561,000
kWh
$5,614
-
kW-mo/yr
- - - - - -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $33,252 $1,000 $26,585
501,600
kWh
$6,667
-
kW-mo/yr
- - - - - -
09 2.2136: Install / repair insulation on steam lines $18,821 $1,900 - - $18,821
-
MMBtu
- - - - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $15,188 $28,755 $11,799
222,631
kWh
$2,959
-
kW-mo/yr
- - $430 - - -
11 2.2163: Use minimum steam operating pressure $7,900 - - - $7,900
-
MMBtu
- - - - -
12 2.4234: Cool compressor air intake with heat exchanger $8,318 $19,000 - - - - - - - $8,318
-
Tgal
13 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $4,240 - $4,240
80,000
kWh
- - - - - - -
14 2.7142: Utilize higher efficiency lamps and/or ballasts $2,509 $3,815 $2,144
40,445
kWh
$365
-
kW-mo/yr
- - - - - -
15 4.131: Modify process to reduce material use/cost $1,436 - - - $1,436
-
MMBtu
- - - - -
TOTAL RECOMMENDED $1,454,462 $488,143 $74,501
1,405,676
kWh
$15,605
-
kW-mo/yr
$595,331
-
MMBtu
$3,600
-
lb
$466,990 $237,600 $6,000 $54,835
-
Tgal
TOTAL IMPLEMENTED $189,799 $128,815 $62,702
1,183,045
kWh
$12,646
-
kW-mo/yr
$99,037
-
MMBtu
- - - $6,000 $9,414
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs