| Assessment Year | 2007 |
|---|---|
| Principal Product | Brushroll Products |
| NAICS | 339994: Broom, Brush, and Mop Manufacturing |
| SIC | 3991: Brooms and Brushes |
| Sales Range | $10 M to 50M |
| # of Employees | 83 |
| Plant Area |
56,000
ft2
|
| Annual Production | 3,200,000
pieces
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $193,878 | 1,556,126 |
kWh
|
$0.12 |
| Natural Gas | $61,443 | 4,659 |
MMBtu
|
$13.19 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $30,128 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,484 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,208 | $22,275 |
$6,513
99,440
kWh
|
$4,281
-
kW-mo/yr
|
- | $414 | |
| 02 | 2.2437: Recover waste heat from equipment | $5,342 | $600 | - | - |
$5,342
-
MMBtu
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,341 | $7,780 |
$3,341
51,400
kWh
|
- | - | $1,000 | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,639 | $8,838 |
$2,281
34,832
kWh
|
$850
-
kW-mo/yr
|
- | $508 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,830 | $10,000 |
$917
14,000
kWh
|
$603
-
kW-mo/yr
|
- | $310 | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,180 | - |
$468
10,875
kWh
|
$712
-
kW-mo/yr
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,102 | $3,285 |
$665
10,152
kWh
|
$437
-
kW-mo/yr
|
- | - | |
| 08 | 2.2511: Insulate bare equipment | $1,182 | $1,450 | - | - |
$1,182
-
MMBtu
|
- | |
| 09 | 2.7122: Disconnect ballasts | $304 | - |
$120
2,808
kWh
|
$184
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $30,128 | $54,228 |
$14,305
223,507
kWh
|
$7,067
-
kW-mo/yr
|
$6,524
-
MMBtu
|
$2,232 | ||
| TOTAL IMPLEMENTED | $1,484 | - |
$588
13,683
kWh
|
$896
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs