| Assessment Year | 2007 |
|---|---|
| Principal Product | Abrasives |
| NAICS | 327910: Abrasive Product Manufacturing |
| SIC | 3291: Abrasive Products |
| Sales Range | $10 M to 50M |
| # of Employees | 174 |
| Plant Area |
259,000
ft2
|
| Annual Production | 40,000,000
pieces
|
| Production Hrs. Annual | 2,040
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $103,448 | 2,719,360 |
kWh
|
$0.038 |
| Electricity Demand | $118,133 | 8,508 |
kW-mo/yr
|
$13.88 |
| Natural Gas | $286,000 | 25,978 |
MMBtu
|
$11.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $92,635 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $33,570 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $25,211 | - | - | - | - | - | - | $25,211 | |
| 02 | 2.3511: Use plant owned transformers or lease transformers | $23,789 | $95,156 | - | - | $23,789 | - | - | - | |
| 03 | 2.2511: Insulate bare equipment | $22,493 | $9,310 | - | - | - |
$22,493
-
MMBtu
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,650 | $33,580 |
$2,299
74,162
kWh
|
$4,040
-
kW-mo/yr
|
- | - | $311 | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,048 | $19,730 |
$1,883
60,741
kWh
|
$3,970
-
kW-mo/yr
|
- | - | $195 | - | |
| 06 | 2.2437: Recover waste heat from equipment | $5,706 | $7,000 |
$1,042
33,600
kWh
|
$667
-
kW-mo/yr
|
- |
$3,997
-
MMBtu
|
- | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,709 | $1,465 |
$1,042
33,600
kWh
|
$667
-
kW-mo/yr
|
- | - | - | - | |
| 08 | 2.7122: Disconnect ballasts | $1,029 | $180 |
$331
10,672
kWh
|
$698
-
kW-mo/yr
|
- | - | - | - | |
| TOTAL RECOMMENDED | $92,635 | $166,421 |
$6,597
212,775
kWh
|
$10,042
-
kW-mo/yr
|
$23,789 |
$26,490
-
MMBtu
|
$506 | $25,211 | ||
| TOTAL IMPLEMENTED | $33,570 | $35,045 |
$3,341
107,762
kWh
|
$4,707
-
kW-mo/yr
|
- | - | $311 | $25,211 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs