Assessment Year | 2006 |
---|---|
Principal Product | Caskets |
NAICS | 339995: Burial Casket Manufacturing |
SIC | 3995: Burial Caskets |
Sales Range | $100 M to 500M |
# of Employees | 250 |
Plant Area |
175,000
ft2
|
Annual Production | 73,000
pieces
|
Production Hrs. Annual | 4,500
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $118,353 | 6,315,764 |
kWh
|
$0.019 |
Electricity Demand | $239,725 | 17,016 |
kW-mo/yr
|
$14.09 |
Natural Gas | $730,082 | 62,478 |
MMBtu
|
$11.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $369,855 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $264,148 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7221: Lower temperature during the winter season and vice-versa | $212,325 | $9,000 | - | - | - |
$212,325
-
MMBtu
|
- | - | |
02 | 2.3511: Use plant owned transformers or lease transformers | $36,368 | $5,000 | - | - | $37,368 | - | $(-1,000.0) | - | |
03 | 2.4311: Recover mechanical energy | $33,450 | $32 | - | - | - |
$33,450
-
MMBtu
|
- | - | |
04 | 2.7314: Reduce ventilation air | $38,385 | - | - | - | - |
$38,385
-
MMBtu
|
- | - | |
05 | 2.2531: Re-size charging openings or add movable cover or door | $14,908 | $5,056 |
$(-242.0)
(-11,520)
kWh
|
$(-440.0)
-
kW-mo/yr
|
- |
$15,590
-
MMBtu
|
- | - | |
06 | 2.7122: Disconnect ballasts | $9,527 | $1,440 |
$3,379
160,911
kWh
|
$6,148
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7135: Install occupancy sensors | $5,203 | $21,789 |
$1,707
81,287
kWh
|
$3,496
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,043 | $9,000 |
$4,043
192,500
kWh
|
- | - | - | - | - | |
09 | 2.2532: Use only amount of air necessary to prevent explosion hazard | $3,767 | $700 | - | - | - |
$3,767
-
MMBtu
|
- | - | |
10 | 2.4131: Size electric motors for peak operating efficiency | $2,932 | - |
$1,040
49,500
kWh
|
$1,892
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,665 | - |
$945
45,000
kWh
|
$1,720
-
kW-mo/yr
|
- | - | - | - | |
12 | 3.4115: Recover and reuse cooling water | $2,635 | $1,000 | - | - | - | - | - |
$2,635
-
Tgal
|
|
13 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,293 | - |
$806
38,400
kWh
|
$1,487
-
kW-mo/yr
|
- | - | - | - | |
14 | 2.7134: Use photocell controls | $733 | $308 |
$184
11,440
kWh
|
$549
-
kW-mo/yr
|
- | - | - | - | |
15 | 2.4235: Remove or close off unneeded compressed air lines | $376 | $214 |
$376
17,920
kWh
|
- | - | - | - | - | |
16 | 2.2511: Insulate bare equipment | $245 | $110 | - | - | - |
$245
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $369,855 | $53,649 |
$12,238
585,438
kWh
|
$14,852
-
kW-mo/yr
|
$37,368 |
$303,762
-
MMBtu
|
$(-1,000.0) |
$2,635
-
Tgal
|
||
TOTAL IMPLEMENTED | $264,148 | $32,679 |
$6,215
298,638
kWh
|
$11,913
-
kW-mo/yr
|
- |
$246,020
-
MMBtu
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs