ITAC Assessment: UD0714
ITAC logo
ITAC Assessment: UD0714
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Powder coating and electro-coating for metal castings
NAICS 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 30
Plant Area 44,000
ft2
Annual Production 400,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,757 947,080
kWh
Electricity Demand $45,434 3,552
kW-mo/yr
Natural Gas $120,029 12,967
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $67,024 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $28,348

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Personnel Changes Savings Primary Product Savings
01 4.131: Modify process to reduce material use/cost $14,094 $5,000 - - - - - $14,094 -
02 4.445: Install equipment to move product $13,500 $10,000 - - - - - $13,500 -
03 4.621: Use fixtures to reduce machine changeout times $12,150 $1,000 - - - - - $12,150 -
04 2.2212: Use minimum safe oven ventilation $6,825 $3,000 - - $6,825
-
MMBtu
- - - -
05 2.7241: Install outside air damper / economizer on hvac unit $4,482 $2,000 $4,482
54,662
kWh
- - - - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $3,427 $14,204 $961
31,000
kWh
$2,466
-
kW-mo/yr
- - - - -
07 4.513: Re-arrange equipment layout to reduce labor costs $2,772 $165 - - - - - $2,772 -
08 2.2212: Use minimum safe oven ventilation $1,972 $150 - - $1,972
-
MMBtu
- - - -
09 3.4151: Minimize water usage $1,311 $1,200 - - - $1,311
-
Tgal
- - -
10 2.1233: Analyze flue gas for proper air/fuel ratio $1,296 - - - $1,296
-
MMBtu
- - - -
11 3.4151: Minimize water usage $1,138 $350 - - - $787
-
Tgal
$351
-
gal
- -
12 2.6121: Reduce hot water temperature to the minimum required $1,000 $4,000 - - - - - - $1,000
13 2.4131: Size electric motors for peak operating efficiency $928 $200 $260
8,400
kWh
$668
-
kW-mo/yr
- - - - -
14 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $884 $330 $248
8,000
kWh
$636
-
kW-mo/yr
- - - - -
15 2.4231: Reduce the pressure of compressed air to the minimum required $884 - $248
8,000
kWh
$636
-
kW-mo/yr
- - - - -
16 2.2511: Insulate bare equipment $361 $650 - - $361
-
MMBtu
- - - -
TOTAL RECOMMENDED $67,024 $42,249 $6,199
110,062
kWh
$4,406
-
kW-mo/yr
$10,454
-
MMBtu
$2,098
-
Tgal
$351
-
gal
$42,516 $1,000
TOTAL IMPLEMENTED $28,348 $5,865 $248
8,000
kWh
$636
-
kW-mo/yr
$10,093
-
MMBtu
$2,098
-
Tgal
$351
-
gal
$14,922 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Personnel Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs