ITAC Assessment: UD0699
ITAC logo
ITAC Assessment: UD0699
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Pretzels and Corn Extruded Products
NAICS 331222: Steel Wire Drawing
SIC 2052: Cookies and Crackers
Sales Range $50
M
to 100
M
# of Employees 240
Plant Area 200,000
ft2
Annual Production 40,000,000
pieces
Production Hrs. Annual 6,490
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $208,461 8,297,280
kWh
Electricity Demand $147,742 16,164
kW-mo/yr
Natural Gas $780,411 143,968
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $512,462 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $312,849

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings Increase in Production Savings
01 4.111: Add equipment/ operators to reduce production bottleneck $96,000 $204,300 - - - - - - - $96,000
02 2.2443: Re-use or recycle hot or cold process exhaust air $85,223 $13,240 - - $85,223
-
MMBtu
- - - - -
03 2.1321: Replace fossil fuel equipment with electrical equipment $297,217 - - - $46,429
-
MMBtu
$28,984
-
Tgal
$21,804
-
gal
- $200,000 -
04 2.7241: Install outside air damper / economizer on hvac unit $18,114 - $14,260
570,382
kWh
- $3,854
-
MMBtu
- - - - -
05 2.7122: Disconnect ballasts $7,031 $377 $4,329
175,219
kWh
$2,702
-
kW-mo/yr
- - - - - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $3,689 - $2,271
90,854
kWh
$1,418
-
kW-mo/yr
- - - - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $3,162 $8,406 $1,947
77,880
kWh
$1,215
-
kW-mo/yr
- - - - - -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $975 $255 $600
24,012
kWh
$375
-
kW-mo/yr
- - - - - -
09 2.4111: Utilize energy-efficient belts and other improved mechanisms $775 - $413
16,500
kWh
$334
-
kW-mo/yr
- - - $28 - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $276 $890 $166
6,662
kWh
$110
-
kW-mo/yr
- - - - - -
TOTAL RECOMMENDED $512,462 $227,468 $23,986
961,509
kWh
$6,154
-
kW-mo/yr
$135,506
-
MMBtu
$28,984
-
Tgal
$21,804
-
gal
$28 $200,000 $96,000
TOTAL IMPLEMENTED $312,849 $9,038 $9,560
384,465
kWh
$6,044
-
kW-mo/yr
$46,429
-
MMBtu
$28,984
-
Tgal
$21,804
-
gal
$28 $200,000 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs