ITAC Assessment: UD0695
ITAC logo
ITAC Assessment: UD0695
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Variable Transformers / UPS
NAICS 334416: Capacitor, Resistor, Coil, Transformer, and Other Inductor Manufacturing
SIC 3677: Electronic Coils, Transformers, and Other Inductors
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 121,887
ft2
Annual Production 10,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $32,676 967,061
kWh
Electricity Demand $44,181 3,516
kW-mo/yr
Natural Gas $22,780 2,907
MMBtu
Fuel Oil #2 $40,185 5,885
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $98,417 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $37,670

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #2 Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Product Savings By-product Production Savings
01 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $42,439 - $9,405
300,000
kWh
$55,692
-
kW-mo/yr
$2,916
-
MMBtu
$(-25,574.0)
-
MMBtu
- - - - -
02 4.446: Automate finishing process $14,454 $20,000 - - - - - - $9,204 $5,250 -
03 2.1133: Adjust burners for efficient operation $7,720 - - - $7,720
-
MMBtu
- - - - - -
04 2.2211: Use optimum temperature $7,076 $9 $1,984
64,000
kWh
$5,092
-
kW-mo/yr
- - - - - - -
05 2.7224: Reduce space conditioning during non-working hours $7,056 - - - $7,056
-
MMBtu
- - - - - -
06 4.731: Advertise product or service $7,000 $(-40,240.0) - - - - - - - $7,000 -
07 2.3212: Optimize plant power factor $3,434 - - - $3,434
-
MMBtu
- - - - - -
08 2.2212: Use minimum safe oven ventilation $2,564 - - - $2,564
-
MMBtu
- - - - - -
09 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown $2,331 $175 $50
1,563
kWh
- $2,281
-
MMBtu
- - - - - -
10 3.5316: Contract a wood pallet recycling company $1,110 - - - - - - $1,200
-
lb
$(-390.0) - $300
11 2.1231: Establish burner maintenance schedule for boilers $784 - - - $784
-
MMBtu
- - - - - -
12 2.1233: Analyze flue gas for proper air/fuel ratio $729 - - - $729
-
MMBtu
- - - - - -
13 2.7142: Utilize higher efficiency lamps and/or ballasts $397 $756 $130
4,200
kWh
$267
-
kW-mo/yr
- - - - - - -
14 3.4116: Meter recycled water (to reduce sewer charges) $420 $340 - - - - $420
-
Tgal
- - - -
15 2.7229: Air condition only space necessary $339 - $339
3,355
kWh
- - - - - - - -
16 2.7122: Disconnect ballasts $327 $7 $107
3,450
kWh
$220
-
kW-mo/yr
- - - - - - -
17 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $237 $213 $78
2,500
kWh
$159
-
kW-mo/yr
- - - - - - -
TOTAL RECOMMENDED $98,417 $(-18,740.0) $12,093
379,068
kWh
$61,430
-
kW-mo/yr
$27,484
-
MMBtu
$(-25,574.0)
-
MMBtu
$420
-
Tgal
$1,200
-
lb
$8,814 $12,250 $300
TOTAL IMPLEMENTED $37,670 $(-39,080.0) $2,688
79,068
kWh
$5,738
-
kW-mo/yr
$21,134
-
MMBtu
- - $1,200
-
lb
$(-390.0) $7,000 $300
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #2 Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Product Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs