ITAC Assessment: UD0688
ITAC logo
ITAC Assessment: UD0688
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Powdered metal products
NAICS 332117: Powder Metallurgy Part Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 95,000
ft2
Annual Production 40,000,000
pieces
Production Hrs. Annual 6,600
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $306,448 11,781,600
kWh
Electricity Demand $195,138 21,144
kW-mo/yr
Natural Gas $99,220 13,135
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $789,907 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $212,922

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Gas Savings Water Disposal Savings Other Liquid (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.2314: Replace heat treating oven with more efficient unit $525,435 $1,000,000 - - - $23,935
-
MMBtu
- - $428,400 $73,100
02 2.2211: Use optimum temperature $143,925 $500,000 $81,525
3,135,552
kWh
$62,400
-
kW-mo/yr
- - - - - -
03 2.4235: Remove or close off unneeded compressed air lines $31,450 $7,250 $16,475
633,600
kWh
$14,975
-
kW-mo/yr
- - - - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $15,315 $40,500 $7,895
303,600
kWh
$7,175
-
kW-mo/yr
- - - - $(-1,355.0) $1,600
05 3.4111: Use closed cycle process to minimize waste water production $12,457 $31,250 - - $(-5,715.0)
-
MMBtu
- - $18,172
-
gal
- -
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $11,875 $7,400 $7,040
270,816
kWh
$4,835
-
kW-mo/yr
- - - - - -
07 2.2443: Re-use or recycle hot or cold process exhaust air $10,025 $30,885 - - $10,025
-
MMBtu
- - - - -
08 2.4235: Remove or close off unneeded compressed air lines $10,000 $1,040 $10,000
385,200
kWh
- - - - - - -
09 2.6218: Turn off equipment when not in use $5,165 $6,370 $3,730
143,633
kWh
$1,435
-
kW-mo/yr
- - - - - -
10 2.7111: Reduce illumination to minimum necessary levels $4,750 $1,005 $2,490
95,700
kWh
$2,260
-
kW-mo/yr
- - - - - -
11 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,745 $470 $2,185
84,000
kWh
$1,560
-
kW-mo/yr
- - - - - -
12 3.4116: Meter recycled water (to reduce sewer charges) $3,670 $6,000 - - - - $3,670
-
Tgal
- - -
13 2.6211: Conserve energy by efficient use of vending machines $2,840 - - - $2,840
-
MMBtu
- - - - -
14 2.7124: Make a practice of turning off lights when not needed $2,460 - $2,460
94,600
kWh
- - - - - - -
15 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,100 $1,500 $1,100
42,240
kWh
$1,000
-
kW-mo/yr
- - - - - -
16 2.2514: Cover open tanks $2,010 $2,440 $660
25,200
kWh
$550
-
kW-mo/yr
$800
-
MMBtu
- - - - -
17 2.7314: Reduce ventilation air $1,805 $73 - - $1,805
-
MMBtu
- - - - -
18 2.2511: Insulate bare equipment $880 $1,820 - - $880
-
MMBtu
- - - - -
TOTAL RECOMMENDED $789,907 $1,638,003 $135,560
5,214,141
kWh
$96,190
-
kW-mo/yr
$10,635
-
MMBtu
$23,935
-
MMBtu
$3,670
-
Tgal
$18,172
-
gal
$427,045 $74,700
TOTAL IMPLEMENTED $212,922 $548,200 $116,375
4,476,585
kWh
$80,370
-
kW-mo/yr
$(-1,995.0)
-
MMBtu
- - $18,172
-
gal
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Gas Savings Water Disposal Savings Other Liquid (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs