ITAC Assessment: UD0686
ITAC logo
ITAC Assessment: UD0686
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Heat treated parts
NAICS 332811: Metal Heat Treating
SIC 3398: Metal Heat Treating
Sales Range $1
M
to 5
M
# of Employees 15
Plant Area 20,000
ft2
Annual Production 3,812,630
lb
Production Hrs. Annual 6,240
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,647 1,772,000
kWh
Electricity Demand $75,156 5,712
kW-mo/yr
Natural Gas $134,023 15,351
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $36,460 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,297

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.2414: Use waste heat from hot flue gases to preheat $17,224 $7,681 - - $17,224
-
MMBtu
- -
02 2.2514: Cover open tanks $6,907 $1,110 $3,243
120,120
kWh
$3,341
-
kW-mo/yr
$323
-
MMBtu
- -
03 2.8114: Change rate schedules or other changes in utility service $4,095 - - - - - $4,095
04 3.1191: Change procedures / equipment / operating conditions $3,750 - - - - $3,750 -
05 2.5111: Convert from indirect to direct fired systems $2,043 $2,478 - - $2,043
-
MMBtu
- -
06 2.7122: Disconnect ballasts $885 $667 $455
16,848
kWh
$430
-
kW-mo/yr
- - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $620 $240 $320
11,860
kWh
$300
-
kW-mo/yr
- - -
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $392 $450 $205
7,605
kWh
$159
-
kW-mo/yr
- - $28
09 4.821: Pay bills on time to avoid late fees $285 - - - - $285 -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $196 $297 $101
3,744
kWh
$95
-
kW-mo/yr
- - -
11 2.2312: Minimize non-essential material in heat treatment process $63 $15 - - $63
-
MMBtu
- -
TOTAL RECOMMENDED $36,460 $12,938 $4,324
160,177
kWh
$4,325
-
kW-mo/yr
$19,653
-
MMBtu
$4,035 $4,123
TOTAL IMPLEMENTED $1,297 $690 $525
19,465
kWh
$459
-
kW-mo/yr
- $285 $28
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs