Assessment Year | 2003 |
---|---|
Principal Product | rocker arms |
NAICS | 336310: Motor Vehicle Gasoline Engine and Engine Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $100 M to 500M |
# of Employees | 171 |
Plant Area |
118,136
ft2
|
Annual Production | 453,000
pieces
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $280,389 | 13,094,400 |
kWh
|
$0.021 |
Electricity Demand | $307,485 | 27,120 |
kW-mo/yr
|
$11.34 |
Natural Gas | $108,963 | 18,184 |
MMBtu
|
$5.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $118,211 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,211 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $27,674 | $15,870 | - | - |
$27,674
-
MMBtu
|
- | - | - | |
02 | 2.2437: Recover waste heat from equipment | $27,255 | $5,000 | - | - |
$27,255
-
MMBtu
|
- | - | - | |
03 | 3.4116: Meter recycled water (to reduce sewer charges) | $21,300 | $11,000 | - | - | - | - |
$21,300
-
gal
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,809 | $47,488 |
$6,722
320,100
kWh
|
$6,600
-
kW-mo/yr
|
- | - | - | $487 | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,790 | $3,000 |
$4,435
211,200
kWh
|
$4,355
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,062 | $5,376 |
$3,334
158,746
kWh
|
$2,885
-
kW-mo/yr
|
- | - | - | $843 | |
07 | 2.1116: Improve combustion control capability | $4,800 | $2,000 | - | - | - |
$4,800
-
MMBtu
|
- | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,025 | $1,000 |
$1,525
72,600
kWh
|
$1,500
-
kW-mo/yr
|
- | - | - | - | |
09 | 4.625: Develop standard operating procedures | $2,596 | - |
$46
5,037
kWh
|
- | - | - | - | $2,550 | |
10 | 2.7122: Disconnect ballasts | $1,534 | $116 |
$776
36,960
kWh
|
$758
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.7135: Install occupancy sensors | $366 | $428 |
$366
17,408
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $118,211 | $91,278 |
$17,204
822,051
kWh
|
$16,098
-
kW-mo/yr
|
$54,929
-
MMBtu
|
$4,800
-
MMBtu
|
$21,300
-
gal
|
$3,880 | ||
TOTAL IMPLEMENTED | $19,211 | $6,000 |
$6,006
288,837
kWh
|
$5,855
-
kW-mo/yr
|
- |
$4,800
-
MMBtu
|
- | $2,550 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs