ITAC Assessment: UD0681
ITAC logo
ITAC Assessment: UD0681
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Resistor networks
NAICS 334416: Capacitor, Resistor, Coil, Transformer, and Other Inductor Manufacturing
SIC 3676: Electronic Resistors
Sales Range $10
M
to 50
M
# of Employees 220
Plant Area 250,000
ft2
Annual Production 45,650,000
pieces
Production Hrs. Annual 7,200
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $132,036 11,512,800
kWh
Electricity Demand $396,110 25,488
kW-mo/yr
Natural Gas $110,020 20,438
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $139,783 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $90,491

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 4.111: Add equipment/ operators to reduce production bottleneck $82,000 $1,490 - - - $82,000
02 2.3113: Make ice during off peak hours for cooling $26,822 $100,000 $(-2,410.0)
(-219,000)
kWh
$29,232
-
kW-mo/yr
- -
03 2.2414: Use waste heat from hot flue gases to preheat $13,200 $8,060 - - $13,200
-
MMBtu
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,862 $7,947 $1,117
101,520
kWh
$2,745
-
kW-mo/yr
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,840 $700 $1,110
100,800
kWh
$2,730
-
kW-mo/yr
- -
06 2.7314: Reduce ventilation air $2,785 $1,360 $2,785
253,150
kWh
- - -
07 2.7229: Air condition only space necessary $1,800 - $600
53,874
kWh
$1,200
-
kW-mo/yr
- -
08 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown $1,740 - $245
22,080
kWh
$1,495
-
kW-mo/yr
- -
09 2.4235: Remove or close off unneeded compressed air lines $1,095 $1,268 $315
28,800
kWh
$780
-
kW-mo/yr
- -
10 2.4239: Eliminate or reduce compressed air usage $1,095 $91 $315
28,800
kWh
$780
-
kW-mo/yr
- -
11 2.2511: Insulate bare equipment $930 $1,360 - - $930
-
MMBtu
-
12 2.4111: Utilize energy-efficient belts and other improved mechanisms $350 $230 $115
10,512
kWh
$235
-
kW-mo/yr
- -
13 2.7122: Disconnect ballasts $159 $46 $46
4,176
kWh
$113
-
kW-mo/yr
- -
14 2.7135: Install occupancy sensors $105 $160 $105
9,504
kWh
- - -
TOTAL RECOMMENDED $139,783 $122,712 $4,343
394,216
kWh
$39,310
-
kW-mo/yr
$14,130
-
MMBtu
$82,000
TOTAL IMPLEMENTED $90,491 $10,843 $2,008
181,650
kWh
$5,553
-
kW-mo/yr
$930
-
MMBtu
$82,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs