Assessment Year | 2003 |
---|---|
Principal Product | Aluminum beverage cans |
NAICS | 332431: Metal Can Manufacturing |
SIC | 3411: Metal Cans |
Sales Range | $100 M to 500M |
# of Employees | 118 |
Plant Area |
249,500
ft2
|
Annual Production | 2,100,000,000
pieces
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $767,189 | 35,683,200 |
kWh
|
$0.022 |
Electricity Demand | $616,770 | 54,384 |
kW-mo/yr
|
$11.34 |
Natural Gas | $761,108 | 148,860 |
MMBtu
|
$5.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $350,368 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7314: Reduce ventilation air | $241,706 | $(-3,800,000.0) | n/a |
$3,533
160,600
kWh
|
$2,495
-
kW-mo/yr
|
$235,678
-
MMBtu
|
- | - |
02 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $52,385 | $1,125 | n/a |
$30,932
1,405,980
kWh
|
$21,841
-
kW-mo/yr
|
- | - | $(-388.0) |
03 | 3.4116: Meter recycled water (to reduce sewer charges) | $12,046 | $270 | n/a | - | - | - |
$12,046
-
Tgal
|
- |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,330 | $1,100 | n/a |
$4,530
205,600
kWh
|
$7,800
-
kW-mo/yr
|
- | - | - |
05 | 2.4239: Eliminate or reduce compressed air usage | $7,465 | $200 | n/a |
$4,335
197,000
kWh
|
$3,130
-
kW-mo/yr
|
- | - | - |
06 | 2.2628: Utilize a less expensive cooling method | $7,398 | - | n/a |
$4,336
197,100
kWh
|
$3,062
-
kW-mo/yr
|
- | - | - |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,070 | $7,100 | n/a |
$3,525
160,222
kWh
|
$2,545
-
kW-mo/yr
|
- | - | - |
08 | 2.4239: Eliminate or reduce compressed air usage | $5,200 | $1,750 | n/a |
$3,020
137,000
kWh
|
$2,180
-
kW-mo/yr
|
- | - | - |
09 | 2.7122: Disconnect ballasts | $3,797 | $132 | n/a |
$2,205
100,245
kWh
|
$1,592
-
kW-mo/yr
|
- | - | - |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,739 | $3,618 | n/a |
$1,010
45,930
kWh
|
$729
-
kW-mo/yr
|
- | - | - |
11 | 2.7135: Install occupancy sensors | $232 | $110 | n/a |
$232
10,551
kWh
|
- | - | - | - |
TOTAL RECOMMENDED | $350,368 | $(-3,784,595.0) |
$57,658
2,620,228
kWh
|
$45,374
-
kW-mo/yr
|
$235,678
-
MMBtu
|
$12,046
-
Tgal
|
$(-388.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs