Assessment Year | 2003 |
---|---|
Principal Product | Injection molded parts assembly |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 105 |
Plant Area |
42,000
ft2
|
Annual Production | 4,565,000
lb
|
Production Hrs. Annual | 7,344
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $111,746 | 4,194,000 |
kWh
|
$0.027 |
Electricity Demand | $103,181 | 7,980 |
kW-mo/yr
|
$12.93 |
Natural Gas | $7,104 | 995 |
MMBtu
|
$7.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,530 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,175 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,330 | $21,177 |
$2,450
94,190
kWh
|
$3,880
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,500 | $13,580 |
$2,483
95,472
kWh
|
$2,017
-
kW-mo/yr
|
- | - | |
03 | 2.7226: Use computer programs to optimize hvac performance | $3,794 | - |
$3,794
145,933
kWh
|
- | - | - | |
04 | 2.7221: Lower temperature during the winter season and vice-versa | $1,541 | - |
$339
13,504
kWh
|
- |
$1,202
-
MMBtu
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,175 | - |
$650
24,970
kWh
|
$525
-
kW-mo/yr
|
- | - | |
06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,040 | - |
$(-15.0)
(-571)
kWh
|
$1,738
-
kW-mo/yr
|
- | $(-683.0) | |
07 | 2.7135: Install occupancy sensors | $150 | $212 |
$150
5,695
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $18,530 | $34,969 |
$9,851
379,193
kWh
|
$8,160
-
kW-mo/yr
|
$1,202
-
MMBtu
|
$(-683.0) | ||
TOTAL IMPLEMENTED | $1,175 | - |
$650
24,970
kWh
|
$525
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs