Assessment Year | 2002 |
---|---|
Principal Product | Pont of purchase display cabinetry |
NAICS |
n/a
|
SIC | 2541: Wood Office and Store Fixtures, Partitions, Shelving, and Lockers |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
96,000
ft2
|
Annual Production | 10,000
pieces
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $65,941 | 1,391,780 |
kWh
|
$0.047 |
Electricity Demand | $25,416 | 4,236 |
kW-mo/yr
|
$6.00 |
Natural Gas | $8,641 | 1,256 |
MMBtu
|
$6.88 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,195 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,627 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 4.111: Add equipment/ operators to reduce production bottleneck | $12,000 | $12,000 | - | - | $12,000 | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,416 | $5,925 |
$840
24,000
kWh
|
$576
-
kW-mo/yr
|
- | - | |
03 | 3.1191: Change procedures / equipment / operating conditions | $1,152 | $2,800 | - | - | - | $1,152 | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,212 | - |
$1,488
42,500
kWh
|
$1,224
-
kW-mo/yr
|
$(-1,500.0) | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $415 | $200 |
$228
6,500
kWh
|
$187
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $16,195 | $20,925 |
$2,556
73,000
kWh
|
$1,987
-
kW-mo/yr
|
$10,500 | $1,152 | ||
TOTAL IMPLEMENTED | $1,627 | $200 |
$1,716
49,000
kWh
|
$1,411
-
kW-mo/yr
|
$(-1,500.0) | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs