| Assessment Year | 2002 |
|---|---|
| Principal Product | Robotic Systems |
| NAICS |
n/a
|
| SIC | 3569: General Industrial Machinery and Equipment, Not Elsewhere |
| Sales Range | $50 M to 100M |
| # of Employees | 250 |
| Plant Area |
182,000
ft2
|
| Annual Production | 1,418
pieces
|
| Production Hrs. Annual | 3,432
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $93,003 | 3,501,600 |
kWh
|
$0.027 |
| Electricity Demand | $138,786 | 9,864 |
kW-mo/yr
|
$14.07 |
| Natural Gas | $12,488 | 1,431 |
MMBtu
|
$8.73 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $10,094 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,425 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,669 | $17,123 |
$3,097
114,724
kWh
|
$5,572
-
kW-mo/yr
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $557 | $2,052 |
$253
9,373
kWh
|
$304
-
kW-mo/yr
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $450 | $1,698 |
$180
6,656
kWh
|
$270
-
kW-mo/yr
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $418 | - |
$148
5,491
kWh
|
$270
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $10,094 | $20,873 |
$3,678
136,244
kWh
|
$6,416
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $1,425 | $3,750 |
$581
21,520
kWh
|
$844
-
kW-mo/yr
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs