Assessment Year | 2001 |
---|---|
Principal Product | Adhesives and Sealants |
NAICS |
n/a
|
SIC | 2891: Adhesives and Sealants |
Sales Range | $100 M to 500M |
# of Employees | 500 |
Plant Area |
235,830
ft2
|
Annual Production | 246,925,344
lb
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $441,623 | 15,679,745 |
kWh
|
$0.028 |
Electricity Demand | $349,515 | 30,552 |
kW-mo/yr
|
$11.44 |
Natural Gas | $316,132 | 77,023 |
MMBtu
|
$4.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $64,076 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $44,414 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,423 | $42,285 |
$9,080
302,664
kWh
|
$11,737
-
kW-mo/yr
|
- | - | - | $606 | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $17,160 | - | - |
$17,160
-
kW-mo/yr
|
- | - | - | - | |
03 | 3.2176: Increase use of automation | $8,687 | $2,415 | - | - |
$3,395
-
MMBtu
|
- | $5,292 | - | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $8,360 | $500 | - | - |
$8,360
-
MMBtu
|
- | - | - | |
05 | 3.4111: Use closed cycle process to minimize waste water production | $2,615 | $12,800 |
$(-1,735.0)
(-34,690)
kWh
|
- | - |
$4,350
-
Tgal
|
- | - | |
06 | 2.2437: Recover waste heat from equipment | $5,831 | $8,500 |
$681
32,412
kWh
|
$508
-
kW-mo/yr
|
$4,642
-
MMBtu
|
- | - | - | |
TOTAL RECOMMENDED | $64,076 | $66,500 |
$8,026
300,386
kWh
|
$29,405
-
kW-mo/yr
|
$16,397
-
MMBtu
|
$4,350
-
Tgal
|
$5,292 | $606 | ||
TOTAL IMPLEMENTED | $44,414 | $50,785 |
$9,761
335,076
kWh
|
$29,405
-
kW-mo/yr
|
$4,642
-
MMBtu
|
- | - | $606 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs