ITAC Assessment: UD0608
ITAC logo
ITAC Assessment: UD0608
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Gray, Ductile, Alloy, Steel & Iron Casting
NAICS
n/a
SIC 3321: Gray and Ductile Iron Foundries
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 60,000
ft2
Annual Production 15,587,913
lb
Production Hrs. Annual 6,240
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $582,075 14,549,238
kWh
Electricity Demand $100,992 12,624
kW-mo/yr
LPG $109,754 26,124
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $58,121 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $50,153

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 3.4114: Replace city water with recycled water via cooling tower $27,415 $15,000 - - - $27,415
-
Tgal
-
02 3.4116: Meter recycled water (to reduce sewer charges) $13,231 $1,200 - - - - $13,231
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,027 $6,250 $3,395
106,096
kWh
$1,632
-
kW-mo/yr
- - -
04 2.4133: Use most efficient type of electric motors $4,480 $14,755 $3,136
90,270
kWh
$1,344
-
kW-mo/yr
- - -
05 2.2437: Recover waste heat from equipment $4,156 $3,500 - - $4,156
-
MMBtu
- -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,103 - $1,514
47,186
kWh
$589
-
kW-mo/yr
- - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,709 $4,624 $1,035
32,239
kWh
$674
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $58,121 $45,329 $9,080
275,791
kWh
$4,239
-
kW-mo/yr
$4,156
-
MMBtu
$27,415
-
Tgal
$13,231
TOTAL IMPLEMENTED $50,153 $37,205 $6,531
196,366
kWh
$2,976
-
kW-mo/yr
- $27,415
-
Tgal
$13,231
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs