Assessment Year | 2000 |
---|---|
Principal Product | Gray, Ductile, Alloy, Steel & Iron Casting |
NAICS |
n/a
|
SIC | 3321: Gray and Ductile Iron Foundries |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
60,000
ft2
|
Annual Production | 15,587,913
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $582,075 | 14,549,238 |
kWh
|
$0.040 |
Electricity Demand | $100,992 | 12,624 |
kW-mo/yr
|
$8.00 |
LPG | $109,754 | 26,124 |
MMBtu
|
$4.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $58,121 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $50,153 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.4114: Replace city water with recycled water via cooling tower | $27,415 | $15,000 | - | - | - |
$27,415
-
Tgal
|
- | |
02 | 3.4116: Meter recycled water (to reduce sewer charges) | $13,231 | $1,200 | - | - | - | - | $13,231 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,027 | $6,250 |
$3,395
106,096
kWh
|
$1,632
-
kW-mo/yr
|
- | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $4,480 | $14,755 |
$3,136
90,270
kWh
|
$1,344
-
kW-mo/yr
|
- | - | - | |
05 | 2.2437: Recover waste heat from equipment | $4,156 | $3,500 | - | - |
$4,156
-
MMBtu
|
- | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,103 | - |
$1,514
47,186
kWh
|
$589
-
kW-mo/yr
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,709 | $4,624 |
$1,035
32,239
kWh
|
$674
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $58,121 | $45,329 |
$9,080
275,791
kWh
|
$4,239
-
kW-mo/yr
|
$4,156
-
MMBtu
|
$27,415
-
Tgal
|
$13,231 | ||
TOTAL IMPLEMENTED | $50,153 | $37,205 |
$6,531
196,366
kWh
|
$2,976
-
kW-mo/yr
|
- |
$27,415
-
Tgal
|
$13,231 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs