ITAC Assessment: UD0607
ITAC logo
ITAC Assessment: UD0607
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product rubber chemicals
NAICS
n/a
SIC 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 77
Plant Area 58,000
ft2
Annual Production 46,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $141,198 5,022,567
kWh
Electricity Demand $146,791 10,068
kW-mo/yr
LPG $173,031 41,725
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $63,638 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,472

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Administrative Changes Savings
01 3.4111: Use closed cycle process to minimize waste water production $38,566 $50,000 - - - $48,566
-
Tgal
$(-10,000.0)
02 2.7231: Use radiant heater for spot heating $16,600 $20,000 - - $16,600
-
MMBtu
- -
03 2.7124: Make a practice of turning off lights when not needed $3,566 - $3,146
108,441
kWh
$420
-
kW-mo/yr
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,478 $7,485 $1,610
55,686
kWh
$1,868
-
kW-mo/yr
- - -
05 2.2511: Insulate bare equipment $1,428 $3,135 - - $1,428
-
MMBtu
- -
TOTAL RECOMMENDED $63,638 $80,620 $4,756
164,127
kWh
$2,288
-
kW-mo/yr
$18,028
-
MMBtu
$48,566
-
Tgal
$(-10,000.0)
TOTAL IMPLEMENTED $8,472 $10,620 $4,756
164,127
kWh
$2,288
-
kW-mo/yr
$1,428
-
MMBtu
- -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs