ITAC Assessment: UD0601
ITAC logo
ITAC Assessment: UD0601
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Aluminum sand and permanent mold castings
NAICS
n/a
SIC 3365: Aluminum Foundries
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 98,700
ft2
Annual Production 4,000,000
lb
Production Hrs. Annual 4,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $170,956 8,173,212
kWh
Electricity Demand $238,734 17,016
kW-mo/yr
LPG $350,496 88,363
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $269,256 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $138,600

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 4.621: Use fixtures to reduce machine changeout times $138,600 - - - - - $138,600 -
02 4.445: Install equipment to move product $62,400 $100,000 - - - - $62,400 -
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $55,632 $160,000 $31,705
1,510,258
kWh
$49,498
-
kW-mo/yr
$(-25,571.0)
-
MMBtu
- - -
04 3.5315: Lease / purchase baler; sell cardboard to recycler $6,102 $6,000 - - - $162
-
lb
$(-1,560.0) $7,500
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,846 $6,241 $550
31,946
kWh
$1,296
-
kW-mo/yr
- - - -
06 2.7145: Install skylights $4,676 $6,300 $1,342
63,892
kWh
$3,334
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $269,256 $278,541 $33,597
1,606,096
kWh
$54,128
-
kW-mo/yr
$(-25,571.0)
-
MMBtu
$162
-
lb
$199,440 $7,500
TOTAL IMPLEMENTED $138,600 - - - - - $138,600 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs