Assessment Year | 2000 |
---|---|
Principal Product | Aluminum sand and permanent mold castings |
NAICS |
n/a
|
SIC | 3365: Aluminum Foundries |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
98,700
ft2
|
Annual Production | 4,000,000
lb
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $170,956 | 8,173,212 |
kWh
|
$0.021 |
Electricity Demand | $238,734 | 17,016 |
kW-mo/yr
|
$14.03 |
LPG | $350,496 | 88,363 |
MMBtu
|
$3.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $269,256 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $138,600 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 4.621: Use fixtures to reduce machine changeout times | $138,600 | - | - | - | - | - | $138,600 | - | |
02 | 4.445: Install equipment to move product | $62,400 | $100,000 | - | - | - | - | $62,400 | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $55,632 | $160,000 |
$31,705
1,510,258
kWh
|
$49,498
-
kW-mo/yr
|
$(-25,571.0)
-
MMBtu
|
- | - | - | |
04 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $6,102 | $6,000 | - | - | - |
$162
-
lb
|
$(-1,560.0) | $7,500 | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,846 | $6,241 |
$550
31,946
kWh
|
$1,296
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7145: Install skylights | $4,676 | $6,300 |
$1,342
63,892
kWh
|
$3,334
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $269,256 | $278,541 |
$33,597
1,606,096
kWh
|
$54,128
-
kW-mo/yr
|
$(-25,571.0)
-
MMBtu
|
$162
-
lb
|
$199,440 | $7,500 | ||
TOTAL IMPLEMENTED | $138,600 | - | - | - | - | - | $138,600 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs