Assessment Year | 2000 |
---|---|
Principal Product | Custom bar soap products |
NAICS |
n/a
|
SIC | 2841: Soap and Other Detergents, Except Specialty Cleaners |
Sales Range | $10 M to 50M |
# of Employees | 350 |
Plant Area |
250,000
ft2
|
Annual Production | 8,000,000
lb
|
Production Hrs. Annual | 6,732
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $73,274 | 3,332,063 |
kWh
|
$0.022 |
Electricity Demand | $170,474 | 12,168 |
kW-mo/yr
|
$14.01 |
Natural Gas | $167,223 | 50,442 |
MMBtu
|
$3.32 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,279,544 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $37,854 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.441: Install automatic packing equipment | $1,210,579 | $375,000 |
$(-240.0)
(-11,430)
kWh
|
$(-941.0)
-
kW-mo/yr
|
- | - | - | $1,211,760 | - | |
02 | 3.4111: Use closed cycle process to minimize waste water production | $22,073 | $34,288 |
$(-3,084.0)
(-146,835)
kWh
|
$(-6,052.0)
-
kW-mo/yr
|
- |
$31,209
-
Tgal
|
- | - | - | |
03 | 2.2121: Increase amount of condensate returned | $15,756 | $18,000 | - | - |
$9,173
-
MMBtu
|
$4,179
-
Tgal
|
$2,404
-
lb
|
- | - | |
04 | 3.8314: Purchase high materials in returnable bulk containers | $13,603 | - | - | - | - | - |
$(-3,227.0)
-
lb
|
$16,830 | - | |
05 | 2.8118: Check for accuracy of utility / power meters | $9,640 | - | - | - | - | - | - | - | $9,640 | |
06 | 2.2163: Use minimum steam operating pressure | $3,333 | - | - | - |
$3,333
-
MMBtu
|
- | - | - | - | |
07 | 2.7135: Install occupancy sensors | $1,752 | $726 |
$356
16,999
kWh
|
$1,396
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 3.4114: Replace city water with recycled water via cooling tower | $1,720 | $500 | - | - | - |
$1,720
-
Tgal
|
- | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,088 | $4,253 |
$397
18,757
kWh
|
$691
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $1,279,544 | $432,767 |
$(-2,571.0)
(-122,509)
kWh
|
$(-4,906.0)
-
kW-mo/yr
|
$12,506
-
MMBtu
|
$37,108
-
Tgal
|
$(-823.0)
-
lb
|
$1,228,590 | $9,640 | ||
TOTAL IMPLEMENTED | $37,854 | $39,041 |
$(-2,687.0)
(-128,078)
kWh
|
$(-5,361.0)
-
kW-mo/yr
|
$3,333
-
MMBtu
|
$32,929
-
Tgal
|
- | - | $9,640 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs