Assessment Year | 2000 |
---|---|
Principal Product | burlap bags |
NAICS |
n/a
|
SIC | 2393: Textile Bags |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
100,000
ft2
|
Annual Production | 69,000
thousand feet
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $34,355 | 1,237,397 |
kWh
|
$0.028 |
Electricity Demand | $55,548 | 3,948 |
kW-mo/yr
|
$14.07 |
Natural Gas | $50,815 | 12,179 |
MMBtu
|
$4.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $94,823 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $45,777 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.4153: Use counter current rinsing to reduce waste water | $47,817 | $3,000 | - | - | - | - | - | $46,835 |
$982
-
Tgal
|
|
02 | 3.5313: Increase amount of waste recovered for resale | $35,359 | $10,000 | - | - | - |
$35,359
-
lb
|
- | - | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $9,607 | $2,240 |
$1,594
61,254
kWh
|
$4,086
-
kW-mo/yr
|
$2,627
-
MMBtu
|
- | $1,300 | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,229 | $3,038 |
$402
15,240
kWh
|
$827
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.2121: Increase amount of condensate returned | $811 | - | - | - |
$156
-
MMBtu
|
- | - | - |
$655
-
Tgal
|
|
TOTAL RECOMMENDED | $94,823 | $18,278 |
$1,996
76,494
kWh
|
$4,913
-
kW-mo/yr
|
$2,783
-
MMBtu
|
$35,359
-
lb
|
$1,300 | $46,835 |
$1,637
-
Tgal
|
||
TOTAL IMPLEMENTED | $45,777 | $12,240 |
$1,594
61,254
kWh
|
$4,086
-
kW-mo/yr
|
$2,783
-
MMBtu
|
$35,359
-
lb
|
$1,300 | - |
$655
-
Tgal
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs