ITAC Assessment: UD0590
ITAC logo
ITAC Assessment: UD0590
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product burlap bags
NAICS
n/a
SIC 2393: Textile Bags
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 100,000
ft2
Annual Production 69,000
thousand feet
Production Hrs. Annual 6,240
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $34,355 1,237,397
kWh
Electricity Demand $55,548 3,948
kW-mo/yr
Natural Gas $50,815 12,179
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $94,823 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $45,777

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 3.4153: Use counter current rinsing to reduce waste water $47,817 $3,000 - - - - - $46,835 $982
-
Tgal
02 3.5313: Increase amount of waste recovered for resale $35,359 $10,000 - - - $35,359
-
lb
- - -
03 2.4239: Eliminate or reduce compressed air usage $9,607 $2,240 $1,594
61,254
kWh
$4,086
-
kW-mo/yr
$2,627
-
MMBtu
- $1,300 - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,229 $3,038 $402
15,240
kWh
$827
-
kW-mo/yr
- - - - -
05 2.2121: Increase amount of condensate returned $811 - - - $156
-
MMBtu
- - - $655
-
Tgal
TOTAL RECOMMENDED $94,823 $18,278 $1,996
76,494
kWh
$4,913
-
kW-mo/yr
$2,783
-
MMBtu
$35,359
-
lb
$1,300 $46,835 $1,637
-
Tgal
TOTAL IMPLEMENTED $45,777 $12,240 $1,594
61,254
kWh
$4,086
-
kW-mo/yr
$2,783
-
MMBtu
$35,359
-
lb
$1,300 - $655
-
Tgal
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs