| Assessment Year | 2000 |
|---|---|
| Principal Product | compression molded polymer consumer products |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 65 |
| Plant Area |
75,000
ft2
|
| Annual Production | 1,200,000
pieces
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $86,120 | 3,614,889 |
kWh
|
$0.024 |
| Electricity Demand | $126,570 | 9,132 |
kW-mo/yr
|
$13.86 |
| Natural Gas | $21,037 | 4,370 |
MMBtu
|
$4.81 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $321,027 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $39,957 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.211: Consider use / purchase of bulk materials where possible | $240,319 | $400,000 |
$(-3,571.0)
(-169,988)
kWh
|
$(-15,310.0)
-
kW-mo/yr
|
- |
$81,000
-
lb
|
- | $178,200 | - | |
| 02 | 4.511: Expand operations into unused space | $35,731 | - |
$1,526
72,685
kWh
|
$31,965
-
kW-mo/yr
|
- |
$240
-
lb
|
- | $2,000 | - | |
| 03 | 4.122: Develop standard procedures to improve internal yields | $34,765 | - | - | - | - | - | $(-60,000.0) | - | $94,765 | |
| 04 | 2.2437: Recover waste heat from equipment | $5,192 | $640 |
$2,011
95,838
kWh
|
$2,238
-
kW-mo/yr
|
$943
-
MMBtu
|
- | - | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,943 | $6,246 |
$1,136
54,220
kWh
|
$1,807
-
kW-mo/yr
|
- | - | - | - | - | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,077 | $4,500 |
$983
46,893
kWh
|
$1,094
-
kW-mo/yr
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $321,027 | $411,386 |
$2,085
99,648
kWh
|
$21,794
-
kW-mo/yr
|
$943
-
MMBtu
|
$81,240
-
lb
|
$(-60,000.0) | $180,200 | $94,765 | ||
| TOTAL IMPLEMENTED | $39,957 | $640 |
$2,011
95,838
kWh
|
$2,238
-
kW-mo/yr
|
$943
-
MMBtu
|
- | $(-60,000.0) | - | $94,765 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs