Assessment Year | 2000 |
---|---|
Principal Product | Food products |
NAICS |
n/a
|
SIC | 2026: Fluid Milk |
Sales Range | $50 M to 100M |
# of Employees | 190 |
Plant Area |
100,000
ft2
|
Annual Production | 364,000,000
lb
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $230,401 | 7,073,857 |
kWh
|
$0.033 |
Electricity Demand | $288,179 | 15,696 |
kW-mo/yr
|
$18.36 |
Natural Gas | $93,182 | 26,022 |
MMBtu
|
$3.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $676,616 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $23,837 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.131: Modify process to reduce material use/cost | $454,896 | $340,000 | - | - | - | $219,024 | - | - | - | $235,872 | - | |
02 | 3.4131: Minimize contamination of water before treatment | $99,635 | $350,000 | - | - | $(-9,967.0) | $(-12,012.0) | $148,134 | $(-26,520.0) | - | - | - | |
03 | 4.111: Add equipment/ operators to reduce production bottleneck | $96,665 | $5,000 | - | - | - | - | - | - | - | - | $96,665 | |
04 | 3.4151: Minimize water usage | $18,654 | $298 | - | - | - | - | - | - |
$18,654
-
Tgal
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,183 | - |
$1,679
72,978
kWh
|
$3,504
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,583 | - |
$383
18,171
kWh
|
$1,200
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
TOTAL RECOMMENDED | $676,616 | $695,298 |
$2,062
91,149
kWh
|
$4,704
-
kW-mo/yr
|
$(-9,967.0) | $207,012 | $148,134 | $(-26,520.0) |
$18,654
-
Tgal
|
$235,872 | $96,665 | ||
TOTAL IMPLEMENTED | $23,837 | $298 |
$1,679
72,978
kWh
|
$3,504
-
kW-mo/yr
|
- | - | - | - |
$18,654
-
Tgal
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs