| Assessment Year | 1999 |
|---|---|
| Principal Product | complete truck chassis |
| NAICS |
n/a
|
| SIC | 3711: Motor Vehicles and Passenger Car Bodies |
| Sales Range | $10 M to 50M |
| # of Employees | 31 |
| Plant Area |
30,000
ft2
|
| Annual Production | 120
pieces
|
| Production Hrs. Annual | 2,340
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $25,873 | 250,586 |
kWh
|
$0.10 |
| Natural Gas | $14,364 | 3,043 |
MMBtu
|
$4.72 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,362 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,264 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 4.311: Schedule deliveries according to demand | $6,264 | - | - | - | - | $6,264 | |
| 02 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $3,367 | $4,000 | - | - |
$1,200
-
lb
|
$2,167 | |
| 03 | 2.7145: Install skylights | $2,731 | $7,004 |
$496
20,516
kWh
|
$2,235
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $12,362 | $11,004 |
$496
20,516
kWh
|
$2,235
-
kW-mo/yr
|
$1,200
-
lb
|
$8,431 | ||
| TOTAL IMPLEMENTED | $6,264 | - | - | - | - | $6,264 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs