ITAC Assessment: UD0581
ITAC logo
ITAC Assessment: UD0581
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product automotive sub-assemblies, exhaust components, gaskets
NAICS
n/a
SIC 3053: Gaskets, Packing, and Sealing Devices
Sales Range $100
M
to 500
M
# of Employees 150
Plant Area 100,000
ft2
Annual Production 900,000
pieces
Production Hrs. Annual 5,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $102,349 1,031,946
kWh
Natural Gas $13,114 3,408
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $405,007 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $370,588

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings Increase in Production Savings
01 4.431: Train operators for maximum operating efficiency $370,588 $40,000 - - - - $370,588
02 3.5217: Reuse / recycle/ sell paper products $27,501 $6,000 - - $24,147
-
lb
$3,354 -
03 3.6192: Use a less expensive method of waste removal $6,000 - - - - $6,000 -
04 2.4231: Reduce the pressure of compressed air to the minimum required $918 $200 $630
12,016
kWh
$288
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $405,007 $46,200 $630
12,016
kWh
$288
-
kW-mo/yr
$24,147
-
lb
$9,354 $370,588
TOTAL IMPLEMENTED $370,588 $40,000 - - - - $370,588
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs