Assessment Year | 1999 |
---|---|
Principal Product | Machined automotive brake rotors and drums |
NAICS |
n/a
|
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 320 |
Plant Area |
300,000
ft2
|
Annual Production | 7,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $930,300 | 26,107,855 |
kWh
|
$0.036 |
Electricity Demand | $668,653 | 48,348 |
kW-mo/yr
|
$13.83 |
Natural Gas | $272,505 | 77,838 |
MMBtu
|
$3.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $677,856 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $53,856 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 4.441: Install automatic packing equipment | $480,000 | $175,000 | - | - | - | $480,000 | |
02 | 4.423: Move product using mechanical means | $144,000 | $150,000 | - | - | - | $144,000 | |
03 | 2.6242: Minimize operation of equipment maintained in standby condition | $39,515 | $10,000 |
$17,940
780,188
kWh
|
$21,575
-
kW-mo/yr
|
- | - | |
04 | 2.2437: Recover waste heat from equipment | $14,341 | $15,000 |
$(-955.0)
(-41,618)
kWh
|
$(-1,196.0)
-
kW-mo/yr
|
$16,492
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $677,856 | $350,000 |
$16,985
738,570
kWh
|
$20,379
-
kW-mo/yr
|
$16,492
-
MMBtu
|
$624,000 | ||
TOTAL IMPLEMENTED | $53,856 | $25,000 |
$16,985
738,570
kWh
|
$20,379
-
kW-mo/yr
|
$16,492
-
MMBtu
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs