ITAC Assessment: UD0574
ITAC logo
ITAC Assessment: UD0574
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Cinder and concrete blocks
NAICS
n/a
SIC 3271: Concrete Block and Brick
Sales Range $1
M
to 5
M
# of Employees 7
Plant Area 20,000
ft2
Annual Production 1,800,000
pieces
Production Hrs. Annual 2,500
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $3,793 165,592
kWh
Electricity Demand $19,923 1,416
kW-mo/yr
Natural Gas $9,115 1,859
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $121,995 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,572

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Primary Raw Material Savings Primary Product Savings By-product Production Savings Increase in Production Savings
01 4.711: Initiate a total quality management program $53,280 $5,000 - - - - $53,280 - -
02 4.441: Install automatic packing equipment $44,950 $110,000 - - $1,750 - - - $43,200
03 3.1175: Use a different or recycled raw material $11,550 - - - - $11,550 - - -
04 2.3131: Reschedule plant operations or reduce load to avoid peaks $5,572 - - $5,572
-
kW-mo/yr
- - - - -
05 3.7214: Reduce or eliminate waste $6,643 $10,000 $(-910.0)
(-33,705)
kWh
$(-2,847.0)
-
kW-mo/yr
$1,400 - - $9,000 -
TOTAL RECOMMENDED $121,995 $125,000 $(-910.0)
(-33,705)
kWh
$2,725
-
kW-mo/yr
$3,150 $11,550 $53,280 $9,000 $43,200
TOTAL IMPLEMENTED $5,572 - - $5,572
-
kW-mo/yr
- - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs