ITAC Assessment: NV0149
ITAC logo
ITAC Assessment: NV0149
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Mineral Supplements for Cattle Feed
NAICS
n/a
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $1
M
to 5
M
# of Employees 16
Plant Area 30,000
ft2
Annual Production 75,000
ton
Production Hrs. Annual 6,240
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $50,925 1,220,399
kWh
Electricity Demand $42,939 4,627
kW-mo/yr
Electricity Fees $2,489 -
Natural Gas $15,171 2,289
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $60,076 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $342

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $342 $100 $68
1,758
kWh
$268
-
kW-mo/yr
$6 - -
02 2.8114: Change rate schedules or other changes in utility service $454 - - - - - $454
03 4.441: Install automatic packing equipment $37,440 $80,000 - - - $37,440 -
04 4.451: Add additional production shift $21,840 - - - - $21,840 -
TOTAL RECOMMENDED $60,076 $80,100 $68
1,758
kWh
$268
-
kW-mo/yr
$6 $59,280 $454
TOTAL IMPLEMENTED $342 $100 $68
1,758
kWh
$268
-
kW-mo/yr
$6 - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs