Assessment Year | 2000 |
---|---|
Principal Product | Mineral Supplements for Cattle Feed |
NAICS |
n/a
|
SIC | 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats |
Sales Range | $1 M to 5M |
# of Employees | 16 |
Plant Area |
30,000
ft2
|
Annual Production | 75,000
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $50,925 | 1,220,399 |
kWh
|
$0.042 |
Electricity Demand | $42,939 | 4,627 |
kW-mo/yr
|
$9.28 |
Electricity Fees | $2,489 | - |
|
- |
Natural Gas | $15,171 | 2,289 |
MMBtu
|
$6.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $60,076 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $342 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $342 | $100 |
$68
1,758
kWh
|
$268
-
kW-mo/yr
|
$6 | - | - | |
02 | 2.8114: Change rate schedules or other changes in utility service | $454 | - | - | - | - | - | $454 | |
03 | 4.441: Install automatic packing equipment | $37,440 | $80,000 | - | - | - | $37,440 | - | |
04 | 4.451: Add additional production shift | $21,840 | - | - | - | - | $21,840 | - | |
TOTAL RECOMMENDED | $60,076 | $80,100 |
$68
1,758
kWh
|
$268
-
kW-mo/yr
|
$6 | $59,280 | $454 | ||
TOTAL IMPLEMENTED | $342 | $100 |
$68
1,758
kWh
|
$268
-
kW-mo/yr
|
$6 | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs