ITAC Assessment: UD0568
ITAC logo
ITAC Assessment: UD0568
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product electronic measuring equipment and sensors
NAICS
n/a
SIC 3823: Industrial Instruments for Measurement, Display, and Control of Process Variables; and Related Products
Sales Range $10
M
to 50
M
# of Employees 230
Plant Area 110,000
ft2
Annual Production 31,250
pieces
Production Hrs. Annual 3,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $109,304 3,440,211
kWh
Electricity Demand $53,664 8,256
kW-mo/yr
Natural Gas $8,312 1,635
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,193 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,171

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 3.8132: Use less toxic and volatile solvent substitutes $8,393 $3,600 - - - $3,393
-
gal
- - - $5,000
02 3.5217: Reuse / recycle/ sell paper products $5,475 $7,000 - - - - $3,375
-
lb
$(-1,500.0) $3,600 -
03 2.7242: Change zone reheat coils to variable air volume boxes $5,171 $4,000 $906
28,429
kWh
- $4,265
-
MMBtu
- - - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,154 $2,000 $1,814
56,565
kWh
$1,340
-
kW-mo/yr
- - - - - -
TOTAL RECOMMENDED $22,193 $16,600 $2,720
84,994
kWh
$1,340
-
kW-mo/yr
$4,265
-
MMBtu
$3,393
-
gal
$3,375
-
lb
$(-1,500.0) $3,600 $5,000
TOTAL IMPLEMENTED $5,171 $4,000 $906
28,429
kWh
- $4,265
-
MMBtu
- - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs